The questions given below contain two statement numbered I and II giving certain data. You have to decide whether the data given in the statements are sufficient to answer the question. Give answer.
In how many days can A, B and C together finish a piece or work?
I. A and B together can finish the same piece of work in 823 days. B and C together can finish the same piece of work in 1313 days. C and A together can finish the same piece of work in 1137 days.
II. The time taken by A alone to finish the same piece of works is 24 days less than the time taken by C alone to finish the same piece of work.
if statement I alone is sufficient but statement II alone is not sufficient.
if statement II alone is sufficient but statement I alone is not sufficient.
if either statement I or II is sufficient
If both statements I and II together are not sufficient.
The correct Answer is:A
To solve the problem, we need to analyze the information given in both statements and determine if they provide enough data to find out how many days A, B, and C can finish a piece of work together.
1. Understanding the Statements:
- Statement I:
- A and B together can finish the work in 823 days.
- B and C together can finish the work in 1313 days.
- C and A together can finish the work in 1137 days.
- Statement II:
- The time taken by A alone to finish the work is 24 days less than the time taken by C alone.
2. Convert Mixed Numbers to Improper Fractions:
- Convert the days into improper fractions:
- 823=263
- 1313=403
- 1137=807
3. Calculate Work Done Per Day:
- The work done by A and B together in one day is:
A+B=1263=326
- The work done by B and C together in one day is:
B+C=1403=340
- The work done by C and A together in one day is:
C+A=1807=780
4. Setting Up the Equations:
- Let the work done by A, B, and C in one day be a, b, and c respectively.
- From the statements, we can set up the following equations:
a+b=326
b+c=340
c+a=780
5. Adding the Equations:
- Adding all three equations:
(a+b)+(b+c)+(c+a)=326+340+780
- This simplifies to:
2(a+b+c)=326+340+780
6. Finding a Common Denominator:
- The least common multiple of 26, 40, and 80 is 520.
- Convert each fraction:
- 326=60520
- 340=39520
- 780=45.5520
7. Calculate Total Work:
- Adding these fractions gives:
2(a+b+c)=60+39+45.5520=144.5520
- Thus:
a+b+c=144.51040
8. Finding Days to Complete Work:
- The total work done by A, B, and C together in one day is a+b+c.
- The number of days to complete the work is the reciprocal of this value.
Conclusion:
From Statement I alone, we can find the total work done by A, B, and C together and thus determine how many days they will take to finish the work.
Answer: Statement I alone is sufficient to answer the question, while Statement II alone is not sufficient.
- Statement I:
- A and B together can finish the work in 823 days.
- B and C together can finish the work in 1313 days.
- C and A together can finish the work in 1137 days.
- Statement II:
- The time taken by A alone to finish the work is 24 days less than the time taken by C alone.
- Convert the days into improper fractions:
- 823=263
- 1313=403
- 1137=807
- The work done by A and B together in one day is:
A+B=1263=326
- The work done by B and C together in one day is:
B+C=1403=340
- The work done by C and A together in one day is:
C+A=1807=780
- Let the work done by A, B, and C in one day be a, b, and c respectively.
- From the statements, we can set up the following equations:
a+b=326
b+c=340
c+a=780
- Adding all three equations:
(a+b)+(b+c)+(c+a)=326+340+780
- This simplifies to:
2(a+b+c)=326+340+780
- The least common multiple of 26, 40, and 80 is 520.
- Convert each fraction:
- 326=60520
- 340=39520
- 780=45.5520
- Adding these fractions gives:
2(a+b+c)=60+39+45.5520=144.5520
- Thus:
a+b+c=144.51040
- The total work done by A, B, and C together in one day is a+b+c.
- The number of days to complete the work is the reciprocal of this value.
From Statement I alone, we can find the total work done by A, B, and C together and thus determine how many days they will take to finish the work.
Similar Questions
A and B together can do a piece of work in 12 days. While B and C together can do a piece of work in 8 days. C and A together can do a piece of work in 6 days. In how many days will this work be completed by B alone?
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View Solution
Knowledge Check
A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
A12B16C20D24A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?
A5 daysB4 daysC3 daysD2 daysA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A11 daysB21 daysC28 daysD30 days
A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
View SolutionThe question given below contain two statements giving certain data. You have to decide whether the data given in the statements are sufficient for answering the question ?
15 men and 18 women together can complete a work in 10 days. How many days will it take 9 men and 14 women together to complete the same work?
I. 30 men can complete the work in 13 days
II. The amount of work done by a man in one day is 3/4 of the work done by a woman in one day.
View Solution