In these question two equations numebred I and numberd II are given. You have to solve both the equations and find out the correct option.
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?
QuantityI>quantityII
QuantityI≤quantityII
QuantityI≥quantityII
QuantityI<quantityII
The correct Answer is:D
To solve the given problem, we need to analyze both quantities step by step.
Quantity I:
Step 1: Determine the work rates of X, Y, and Z.
- X can finish the work in 12 days, so his work rate is:
Work rate of X=112 of the work per day
- Y can finish the work in 18 days, so his work rate is:
Work rate of Y=118 of the work per day
- Z can finish the work in 9 days, so his work rate is:
Work rate of Z=19 of the work per day
Step 2: Find the total work done in one cycle of 3 days.
- In the first two days, only X works:
Work done by X in 2 days=2×112=212=16
- On the third day, X, Y, and Z work together:
Work done on the 3rd day=112+118+19
To add these fractions, we find a common denominator, which is 36:
=336+236+436=936=14
- Total work done in 3 days:
Total work in 3 days=16+14
Finding a common denominator (12):
=212+312=512
Step 3: Determine how many cycles are needed to complete the work.
- Total work to be done = 1 (whole work)
- Work done in 3 days = 512
Let n be the number of 3-day cycles:
n×512≤1
n≤125=2.4
Thus, n=2 full cycles can be completed.
Step 4: Calculate total work done after 6 days.
- Work done in 6 days:
2×512=1012=56
Step 5: Calculate remaining work and days needed.
- Remaining work:
1−56=16
- On the 7th day, X works alone:
Work done by X on 7th day=112
- On the 8th day, X works again:
Work done by X on 8th day=112
- Total work done in the last two days:
112+112=212=16
Thus, the total number of days to complete the work is:
6+2=8 days
Quantity II:
Step 1: Determine the work rates of A, B, and C.
- A can finish the work in 20 days, so his work rate is:
Work rate of A=120
- B can finish the work in 12 days, so his work rate is:
Work rate of B=112
- C can finish the work in 15 days, so his work rate is:
Work rate of C=115
Step 2: Find the total work done in the first 2 days.
- In 2 days, A, B, and C work together:
Work done in 2 days=2(120+112+115)
Finding a common denominator (60):
=2(360+560+460)=2(1260)=2460=25
Step 3: Determine remaining work after 2 days.
- Remaining work:
1−25=35
Step 4: Calculate work done in the next 4 days (A and C only).
- A and C work together for the next 4 days:
Work done by A and C in 1 day=120+115
Finding a common denominator (60):
=360+460=760
- Work done in 4 days:
4×760=2860=1430=715
Step 5: Calculate remaining work after 6 days.
- Remaining work:
35−715
Finding a common denominator (15):
=915−715=215
Step 6: Calculate how long A works alone to finish the remaining work.
- A's work rate is 120, so time taken to finish 215 work:
Time=215120=215×20=4015=83 days
Step 7: Total days A worked.
- Total days A worked:
2 (initial days)+4 (next days)+83 (final days)=6+83=183+83=263 days
Final Comparison:
- Quantity I: 8 days
- Quantity II: 263≈8.67 days
Conclusion:
Since 8<263, we conclude that Quantity I is less than Quantity II.
Work rate of X=112 of the work per day
- Y can finish the work in 18 days, so his work rate is:
Work rate of Y=118 of the work per day
- Z can finish the work in 9 days, so his work rate is:
Work rate of Z=19 of the work per day
Work done by X in 2 days=2×112=212=16
Work done on the 3rd day=112+118+19
To add these fractions, we find a common denominator, which is 36:
=336+236+436=936=14
Total work in 3 days=16+14
Finding a common denominator (12):
=212+312=512
- Work done in 3 days = 512
n×512≤1
n≤125=2.4
Thus, n=2 full cycles can be completed.
2×512=1012=56
1−56=16
Work done by X on 7th day=112
Work done by X on 8th day=112
112+112=212=16
6+2=8 days
Work rate of A=120
- B can finish the work in 12 days, so his work rate is:
Work rate of B=112
- C can finish the work in 15 days, so his work rate is:
Work rate of C=115
Work done in 2 days=2(120+112+115)
Finding a common denominator (60):
=2(360+560+460)=2(1260)=2460=25
1−25=35
Work done by A and C in 1 day=120+115
Finding a common denominator (60):
=360+460=760
4×760=2860=1430=715
35−715
Finding a common denominator (15):
=915−715=215
Time=215120=215×20=4015=83 days
2 (initial days)+4 (next days)+83 (final days)=6+83=183+83=263 days
- Quantity II: 263≈8.67 days
Since 8<263, we conclude that Quantity I is less than Quantity II.
Similar Questions
A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?A659daysB629daysC6 daysD549daysX, Y and Z can complete a work in 15, 45 and 90 days respectively. In how many days X, Y and Z together can complete the same work?
A12B11C9D10A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
A13 daysB8 daysC6 daysD5 days
A, B and C can do a work in 20, 30 and 60 days respectively. A started the work but every third day three of them work together. Then find the number of days it too them to complete the work.
View SolutionA, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionX and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
View Solution