In these question two equations numebred I and numberd II are given. You have to solve both the equations and find out the correct option.
Quantity I: X, Y and Z can finish a work alone in 12,18 and 9 days respectively. X started the work and Y and Z assisted him on every 3rd day. Find the total number of days in which the work is completed.
Quantity II: A, B and C can finish a work alone in 20,12 and 15 days respectively. All three start working together. After 2 days B left the work. After 4 more days Cleft and the remaining work is completed by A alone. A worked for how many days in all?

A

QuantityI>quantityII

B

QuantityIquantityII

C

QuantityIquantityII

D

QuantityI<quantityII

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the given problem, we need to analyze both quantities step by step.

Quantity I:

Step 1: Determine the work rates of X, Y, and Z.

- X can finish the work in 12 days, so his work rate is:
Work rate of X=112 of the work per day

- Y can finish the work in 18 days, so his work rate is:
Work rate of Y=118 of the work per day

- Z can finish the work in 9 days, so his work rate is:
Work rate of Z=19 of the work per day

Step 2: Find the total work done in one cycle of 3 days.

- In the first two days, only X works:
Work done by X in 2 days=2×112=212=16

- On the third day, X, Y, and Z work together:
Work done on the 3rd day=112+118+19
To add these fractions, we find a common denominator, which is 36:
=336+236+436=936=14

- Total work done in 3 days:
Total work in 3 days=16+14
Finding a common denominator (12):
=212+312=512

Step 3: Determine how many cycles are needed to complete the work.

- Total work to be done = 1 (whole work)
- Work done in 3 days = 512

Let n be the number of 3-day cycles:
n×5121
n125=2.4
Thus, n=2 full cycles can be completed.

Step 4: Calculate total work done after 6 days.

- Work done in 6 days:
2×512=1012=56

Step 5: Calculate remaining work and days needed.

- Remaining work:
156=16

- On the 7th day, X works alone:
Work done by X on 7th day=112

- On the 8th day, X works again:
Work done by X on 8th day=112

- Total work done in the last two days:
112+112=212=16

Thus, the total number of days to complete the work is:
6+2=8 days

Quantity II:

Step 1: Determine the work rates of A, B, and C.

- A can finish the work in 20 days, so his work rate is:
Work rate of A=120

- B can finish the work in 12 days, so his work rate is:
Work rate of B=112

- C can finish the work in 15 days, so his work rate is:
Work rate of C=115

Step 2: Find the total work done in the first 2 days.

- In 2 days, A, B, and C work together:
Work done in 2 days=2(120+112+115)
Finding a common denominator (60):
=2(360+560+460)=2(1260)=2460=25

Step 3: Determine remaining work after 2 days.

- Remaining work:
125=35

Step 4: Calculate work done in the next 4 days (A and C only).

- A and C work together for the next 4 days:
Work done by A and C in 1 day=120+115
Finding a common denominator (60):
=360+460=760

- Work done in 4 days:
4×760=2860=1430=715

Step 5: Calculate remaining work after 6 days.

- Remaining work:
35715
Finding a common denominator (15):
=915715=215

Step 6: Calculate how long A works alone to finish the remaining work.

- A's work rate is 120, so time taken to finish 215 work:
Time=215120=215×20=4015=83 days

Step 7: Total days A worked.

- Total days A worked:
2 (initial days)+4 (next days)+83 (final days)=6+83=183+83=263 days

Final Comparison:

- Quantity I: 8 days
- Quantity II: 2638.67 days

Conclusion:
Since 8<263, we conclude that Quantity I is less than Quantity II.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • X, Y and Z can complete a work in 15, 45 and 90 days respectively. In how many days X, Y and Z together can complete the same work?

    A12
    B11
    C9
    D10
  • A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?

    A13 days
    B8 days
    C6 days
    D5 days