8 men can finish a piece of work in 25 days. 15 women can finish the same piece of work in 16 days. 4 men and 8 women started working together and worked for 10 days. After that 6 more men joined them. How many days will they now take to finish the remaining work?
The correct Answer is:D
To solve the problem step by step, we will first determine the work done by men and women, then calculate the total work, and finally find out how many days it will take to finish the remaining work after some work has already been done.
Step 1: Calculate the total work done by men and women
1. Work done by 8 men in 25 days:
- If 8 men can finish the work in 25 days, the total work (W) can be calculated as:
W=Number of men×Days=8×25=200 man-days
2. Work done by 15 women in 16 days:
- If 15 women can finish the work in 16 days, the total work (W) can also be calculated as:
W=Number of women×Days=15×16=240 woman-days
Step 2: Find the work done by one man and one woman
3. Efficiency of one man (M):
- Since 8 men can complete the work in 25 days:
Efficiency of one man=W8×25=200200=1 unit/day
4. Efficiency of one woman (W):
- Since 15 women can complete the work in 16 days:
Efficiency of one woman=W15×16=240240=1 unit/day
Step 3: Calculate the work done by 4 men and 8 women in 10 days
5. Total efficiency of 4 men and 8 women:
- Work done by 4 men in one day:
Work by 4 men=4×1=4 units/day
- Work done by 8 women in one day:
Work by 8 women=8×1=8 units/day
- Total work done in one day by 4 men and 8 women:
Total work per day=4+8=12 units/day
6. Total work done in 10 days:
Total work in 10 days=12×10=120 units
Step 4: Calculate the remaining work
7. Remaining work:
- Total work is 200 units (from Step 1).
- Work remaining after 10 days:
Remaining work=200−120=80 units
Step 5: Calculate the new team of workers
8. After 10 days, 6 more men join:
- Now, the total number of men is 4+6=10.
- The efficiency of 10 men:
Work by 10 men=10×1=10 units/day
- The efficiency of 8 women remains the same:
Work by 8 women=8×1=8 units/day
- Total efficiency of 10 men and 8 women:
Total work per day=10+8=18 units/day
Step 6: Calculate the number of days to finish the remaining work
9. Days required to finish the remaining work:
Days required=Remaining workTotal efficiency=8018≈4.44 days
- Rounding up, they will take 5 days to finish the remaining work.
Final Answer:
The remaining work will take approximately 5 days to finish.
---
- If 8 men can finish the work in 25 days, the total work (W) can be calculated as:
W=Number of men×Days=8×25=200 man-days
- If 15 women can finish the work in 16 days, the total work (W) can also be calculated as:
W=Number of women×Days=15×16=240 woman-days
- Since 8 men can complete the work in 25 days:
Efficiency of one man=W8×25=200200=1 unit/day
- Since 15 women can complete the work in 16 days:
Efficiency of one woman=W15×16=240240=1 unit/day
- Work done by 4 men in one day:
Work by 4 men=4×1=4 units/day
- Work done by 8 women in one day:
Work by 8 women=8×1=8 units/day
- Total work done in one day by 4 men and 8 women:
Total work per day=4+8=12 units/day
Total work in 10 days=12×10=120 units
- Total work is 200 units (from Step 1).
- Work remaining after 10 days:
Remaining work=200−120=80 units
- Now, the total number of men is 4+6=10.
- The efficiency of 10 men:
Work by 10 men=10×1=10 units/day
- The efficiency of 8 women remains the same:
Work by 8 women=8×1=8 units/day
- Total efficiency of 10 men and 8 women:
Total work per day=10+8=18 units/day
Days required=Remaining workTotal efficiency=8018≈4.44 days
- Rounding up, they will take 5 days to finish the remaining work.
The remaining work will take approximately 5 days to finish.
Similar Questions
Knowledge Check
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
A6 daysB8 daysC623 daysD734 daysIf 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 women will do the same work in how many days ?
A10 daysB12 daysC13 daysD15 days3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?
A3 daysB5 daysC2 daysD4 days
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View Solution