Study the following information carefully and answer the questions given below.
A,B,C,D,and E are five persons employed to complete a job X.
Study the following  information carefully and answer the questions given below.     A,B,C,D,and E are five persons employed to complete a job X.       All the persons worked on the job X for a whole number of days.    Two jobs Y and Z are similar to job X and require the same effort as required by job X.     A, C and E worked on job Z for 2 days each and the remaining job was done by B and D. If the ratio of the number of days for which B and D worked is in the ratio of 20 :21, then what is the number of days for which B worked?
All the persons worked on the job X for a whole number of days.
Two jobs Y and Z are similar to job X and require the same effort as required by job X.
A, C and E worked on job Z for 2 days each and the remaining job was done by B and D. If the ratio of the number of days for which B and D worked is in the ratio of 20 :21, then what is the number of days for which B worked?

A

5 days

B

412days

C

512days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for Study the following information carefully and answer the questions given below. A,B,C,D,and E are five persons employed to complete a job X. All the persons worked on the job X for a whole number of days. Two jobs Y and Z are similar to job X and require the same effort as required by job X. A, C and E worked on job Z for 2 days each and the remaining job was done by B and D. If the ratio of the number of days for which B and D worked is in the ratio of 20 :21, then what is the number of days for which B worked? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Similar Questions


Knowledge Check

  • 24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • 24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

    A30
    B40
    C25
    D50