Study the following information carefully and answer the questions given below.
A,B,C,D,and E are five persons employed to complete a job X.
All the persons worked on the job X for a whole number of days.
Two jobs Y and Z are similar to job X and require the same effort as required by job X.
A, C and E worked on job Z for 2 days each and the remaining job was done by B and D. If the ratio of the number of days for which B and D worked is in the ratio of 20 :21, then what is the number of days for which B worked?
5 days
412days
512days
4 days
The correct Answer is:D
Step by step video, text & image solution for Study the following information carefully and answer the questions given below. A,B,C,D,and E are five persons employed to complete a job X. All the persons worked on the job X for a whole number of days. Two jobs Y and Z are similar to job X and require the same effort as required by job X. A, C and E worked on job Z for 2 days each and the remaining job was done by B and D. If the ratio of the number of days for which B and D worked is in the ratio of 20 :21, then what is the number of days for which B worked? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Similar Questions
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?
View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
E worked on job 'Z' for 5 dyas and the remaining job was completed by A, B and D who worked on alternate days starting with A followed by B and D in thet order. Find the no. of days B worked for ?
View Solution
Knowledge Check
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D5024 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
A30B40C25D50
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If the ratio of number of days for which B and D worked on job X is 4:3 , then find teh difference between of days for which B and D worked ?
View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
A and C worked on job Y working alternatively for 10 days. B and D then worked together for 'x' day . if 136 of the job was still remained, then find the value of 'x' ?
View Solution
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If C worked on job Y with 54times his given efficiency and was assisted by B every 3rd day, then find the time taken by C to complete the job Y ?
View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If A worked on job X for 5 days each and C worked for 3 days. the remaining job was done by E and D. If the ratio of the number of days for which D and E worked is in ratio 1:1, then find the number of days for which C, D and E worked?
View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If the ratio of the number of days for which D and C worked on job Y is 12:5 and completed the work then find the difference between number of days for which C and D worked.
View SolutionA,B,C,D and E are five persons to complete jobs X and Y. Line graph shows the data regarding the number of days taken by these persons to complete the job X and Y.
If B worked on job Y with 4/9 times his work efficiency and assisted by D every 3rd day then find the number of days for which B and D worked to complete the job.
View Solution