Doubtnut Promotions Sticky

Note 1 : All the persons worked on the job X for whole number days.   Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.   If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?
Note 1 : All the persons worked on the job X for whole number days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.
If A,C abd E worked on job Z for 2 days each and the remaining job was done by B and D. if the ratio of no. days for which B and D worked is in ratio 20:21, then find the number of days for which B worked ?

A

50 days

B

412 days

C

512 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D


Work done by A,C and E on job Z in 2 days is-
=210+215+220
=12+8+660
=2660=1330
Remaaining work done by B and D in 20x and 21x
20x12+21x18=1730
60x+42x36=1730102x=17×3630
x=630=15
Required days =20×15=4 days

|
Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?

    A114
    B712
    C184
    D172
  • Question 1 - Select One

    A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

    A2 days
    B3 days
    C1 day
    DNone of these
  • Question 1 - Select One

    If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?

    A36
    B6
    C18
    D12

Similar Questions