Study the following information carefully and answer the questions given below.
A,B,C,D,and E are five persons employed to complete a job X.
Study the following  information carefully and answer the questions given below.     A,B,C,D,and E are five persons employed to complete a job X.        All the persons worked on the job X for a whole number of days.    Two jobs Y and Z are similar to job X and require the same effort as required by job X.   A and C worked on job Y working alternately for 10 days. B and D then worked together for x days. If 1//36 of the job was still to be done, then find the value of x.
All the persons worked on the job X for a whole number of days.
Two jobs Y and Z are similar to job X and require the same effort as required by job X.
A and C worked on job Y working alternately for 10 days. B and D then worked together for x days. If 1/36 of the job was still to be done, then find the value of x.

A

2 days

B

114days

C

113 days

D

1 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for Study the following information carefully and answer the questions given below. A,B,C,D,and E are five persons employed to complete a job X. All the persons worked on the job X for a whole number of days. Two jobs Y and Z are similar to job X and require the same effort as required by job X. A and C worked on job Y working alternately for 10 days. B and D then worked together for x days. If 1//36 of the job was still to be done, then find the value of x. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Similar Questions


Knowledge Check

  • 24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

    A30
    B40
    C25
    D50
  • A man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?

    A5
    B6
    C44202
    D25