If 20 men can build a wall 112 metres long in 6 days, what length of a similar wall can be built by 25 men in 3 days ?
140 metres
44.8 metres
105 metres
70 metres
The correct Answer is:D
To solve the problem, we need to determine how much work can be done by 25 men in 3 days, given that 20 men can build a wall 112 meters long in 6 days. We can use the concept of work, which is defined as the product of the number of men, the number of days, and the hours worked per day. However, since we are not given the hours, we can simplify our calculations.
1. Calculate the total work done by the first group of men:
- The work done (W1) by 20 men in 6 days can be calculated as:
W1=Number of men×Number of days=20×6=120 man-days
- Since they build a wall of 112 meters, we can say:
120 man-days→112 meters
2. Calculate the work done per meter:
- The work done per meter is:
Work per meter=120 man-days112 meters=120112=1514 man-days per meter
3. Calculate the total work that can be done by the second group of men:
- For 25 men working for 3 days, the total work (W2) they can do is:
W2=Number of men×Number of days=25×3=75 man-days
4. Calculate the length of the wall that can be built by the second group:
- To find the length of the wall (L) that can be built by 75 man-days, we use the work per meter calculated earlier:
L=Total workWork per meter=75 man-days1514 man-days per meter=75×1415
- Simplifying this gives:
L=75×1415=5×14=70 meters
Final Answer:
The length of the wall that can be built by 25 men in 3 days is 70 meters.
- The work done (W1) by 20 men in 6 days can be calculated as:
W1=Number of men×Number of days=20×6=120 man-days
- Since they build a wall of 112 meters, we can say:
120 man-days→112 meters
- The work done per meter is:
Work per meter=120 man-days112 meters=120112=1514 man-days per meter
- For 25 men working for 3 days, the total work (W2) they can do is:
W2=Number of men×Number of days=25×3=75 man-days
- To find the length of the wall (L) that can be built by 75 man-days, we use the work per meter calculated earlier:
L=Total workWork per meter=75 man-days1514 man-days per meter=75×1415
- Simplifying this gives:
L=75×1415=5×14=70 meters
The length of the wall that can be built by 25 men in 3 days is 70 meters.
Topper's Solved these Questions
Similar Questions
If 20 men can build a wall 56 metres long in 6 day what length of a similar wall can be built by 35 men in 3 days?
View Solution40 men can build a wall 200 m longin 12 days working 8 h a day. The number of days 30 men will take to build a similar wall 300 m long working 6h per day will be (A) 32 (B) 18 (C) 36 (D) 9
View Solution
Knowledge Check
20 men can build 56 m wall in 6 days. What length of a similar wall can be build by 70 men in 3 days ?
A100mB98mC48mD85m40 men can build a wall 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:
A100B125C150D200If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?
A30B10C18D28
If 36 men can build a wall of 140 m length in 10.5 days, how many men could take 9 days to build a similar type of wall of length 50 m?
View Solution40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day
View Solution36 men can build a wall 140 m long in 21 days , in how many days would 15 men be able to construct a similar wall 50 m long ?
View Solution40 men build a well 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:
View SolutionIf 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?
View Solution