If six men working 8 hours a day earn Rs. 840 per week then 9 men working 6 hours a day will earn per week-----

A

Rs.840

B

Rs.945

C

Rs.1620

D

Rs.1680

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will first determine the total work done by the six men in a week and then find out how much work the nine men can do in a week. Finally, we will calculate their earnings based on the work done.

Step 1: Calculate the total work done by 6 men in a week.

Given:
- Number of men = 6
- Hours worked per day = 8
- Days worked in a week = 7 (assuming a week has 7 days)

Total work done by 6 men in a week can be calculated as:
Total Work=Number of Men×Hours per Day×Days per Week
Total Work=6×8×7=336 man-hours

Step 2: Calculate the earning per man-hour.

From the problem, we know that 6 men earn Rs. 840 for 336 man-hours of work.
Thus, the earning per man-hour is:
Earning per man-hour=Total EarningsTotal Work
Earning per man-hour=840336=2.5 Rs/man-hour

Step 3: Calculate the total work done by 9 men in a week.

Now, we need to calculate the work done by 9 men working 6 hours a day for 7 days.
Total Work by 9 men=9×6×7=378 man-hours

Step 4: Calculate the earnings for 9 men.

Now, we can find out how much 9 men will earn for 378 man-hours of work.
Total Earnings=Total Work×Earning per man-hour
Total Earnings=378×2.5=945 Rs

Final Answer:
Thus, 9 men working 6 hours a day will earn Rs. 945 per week.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 6 persons working 8 hours a day earn 8400 per week, then 9 persons working 6 hours a day will earn per week

    ARs 8400
    BRs 16800
    CRs 9450
    DRs 16200
  • 10 men working 5 hours/day earn Rs 300. How much money will 15 men working 10 hours/day earn?

    ARs 600
    BRs 900
    CRs800
    DRs 6560
  • If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45