The digging work of the DMRC on the Adohini - Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed?
48
24
36
16
The correct Answer is:B
Step by step video, text & image solution for The digging work of the DMRC on the Adohini - Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution
Knowledge Check
- Question 1 - Select One
Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
A48B24C36DNone of these - Question 2 - Select One
Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
A16B24C36D48 - Question 3 - Select One
16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
A4 daysB6 daysC8 daysD10 days
Eight men can do a certain amount of work in 3 days. Sixteen men can do the same amount of work in 6 days. It is true or false.?
View SolutionTwenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View SolutionTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution