The digging work of the DMRC on the Adohini - Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed?

A

48

B

24

C

36

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for The digging work of the DMRC on the Adohini - Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?

    A48
    B24
    C36
    DNone of these
  • Question 2 - Select One

    Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?

    A16
    B24
    C36
    D48
  • Question 3 - Select One

    16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?

    A4 days
    B6 days
    C8 days
    D10 days