A work is done by three person A,B and C. A alone takes 10 hours to complete a single product but B and C working together takes 4 hours, for the completion of the same product. If all of them worked together and completed 14 products. Then how many hours have they worked?
20 hrs
28 hrs
40 hrs
54 hrs
The correct Answer is:C
To solve the problem step by step, let's break down the information provided and calculate how many hours A, B, and C worked together to complete 14 products.
Step 1: Determine the work done by A, B, and C
1. A's Work Rate: A alone takes 10 hours to complete 1 product. Therefore, A's work rate is:
Work Rate of A=1 product10 hours=0.1 products/hour
2. B and C's Work Rate: B and C together take 4 hours to complete 1 product. Therefore, their combined work rate is:
Work Rate of B and C=1 product4 hours=0.25 products/hour
Step 2: Calculate the combined work rate of A, B, and C
3. Combined Work Rate: The combined work rate of A, B, and C is the sum of their individual work rates:
Combined Work Rate=Work Rate of A+Work Rate of B and C
=0.1+0.25=0.35 products/hour
Step 3: Calculate the time taken to complete 1 product
4. Time to complete 1 product: The time taken to complete 1 product by all three working together is the reciprocal of their combined work rate:
Time for 1 product=1 product0.35 products/hour≈2.857 hours
Step 4: Calculate the time taken to complete 14 products
5. Total time for 14 products: To find the total time taken to complete 14 products, multiply the time taken for 1 product by 14:
Total Time=14×2.857≈40 hours
Conclusion
Thus, A, B, and C worked together for 40 hours to complete 14 products.
---
Work Rate of A=1 product10 hours=0.1 products/hour
Work Rate of B and C=1 product4 hours=0.25 products/hour
Combined Work Rate=Work Rate of A+Work Rate of B and C
=0.1+0.25=0.35 products/hour
Time for 1 product=1 product0.35 products/hour≈2.857 hours
Total Time=14×2.857≈40 hours
Similar Questions
Tushar takes 6 hours to complete a piece of work, while Amar completes the same work in 10 hours. If both of them work together, then what is the time required to complete the work?
View SolutionPipes A and B together take 20 hours, B and C together take 15 hours, and C and A together take 12 hours to fill a tank. In what time will the tank be filled if all 3 pipes work together?
View Solution
Knowledge Check
A alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
A1. 6B2. 8C3. 12D4. 10L alone can complete a work in 200 hours. M alone can complete the same work in 150 hours. L, M and N together can complete the same work in 60 hours. In how many hours can N alone complete the work?
A200B240C180D120B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?
A30B15C20D10
A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View SolutionA, B and C working together can do a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?
View SolutionA can do a piece of work in 24 hours while B alone can do it in 16 hours. If A, B and C working together can finish in 8 hours, in how many hours will C alone do the work?
View SolutionB would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?
View SolutionSunny and Paula can complete a piece of work together in 12 hours. While Paula takes 18 hours to complete the work 2 alone, another individual, Jane, takes 45 hours to complete the same piece of work alone. How many hours would it take Sunny and Jane to complete the same work together ?
View Solution