Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days would B take to finish if he had to perform the task alone?

A

15

B

9

C

8

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down systematically.

Step 1: Determine the total work done by A, B, and C together.
Given that A, B, and C can finish the task together in 4 days, we can calculate their combined efficiency.

- Total work = 1 task
- Time taken by A, B, and C together = 4 days

Efficiency of A, B, and C together = Total work / Time taken = 1 task / 4 days = 1/4 tasks per day.

Step 2: Determine the work done by A and C together.
After B quits, A and C finish the remaining work in 6 days.

- Time taken by A and C together = 6 days

Efficiency of A and C together = Total work / Time taken = 1 task / 6 days = 1/6 tasks per day.

Step 3: Set up equations based on efficiencies.
Let the efficiency of A be a, the efficiency of B be b, and the efficiency of C be c.

From Step 1, we have:
1. a+b+c=1/4 (Equation 1)

From Step 2, we have:
2. a+c=1/6 (Equation 2)

Step 4: Solve for B's efficiency.
Now, we can subtract Equation 2 from Equation 1 to find the efficiency of B.

From Equation 1:
a+b+c=1/4

From Equation 2:
a+c=1/6

Subtracting Equation 2 from Equation 1:
(a+b+c)(a+c)=(1/4)(1/6)
This simplifies to:
b=(1/4)(1/6)

Step 5: Find a common denominator and calculate B's efficiency.
The common denominator for 4 and 6 is 12. Therefore:
1/4=3/12and1/6=2/12
Now substituting these values in:
b=(3/12)(2/12)=1/12

Step 6: Calculate the time taken by B to finish the task alone.
Now that we have the efficiency of B, we can find out how long it would take B to complete the task alone.

Using the formula:
Time=Total WorkEfficiency of B
Substituting the values:
Time=1 task1/12 tasks per day=12 days

Final Answer:
B would take 12 days to finish the task alone.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a task in 5 days and the total unit of work to be done is 40 units. If A alone can finish the task in 20 days, then how many days B will take to finish the task if he does alone?

    A623 days
    B613 days
    C7 days
    D2 days
  • Question 2 - Select One

    X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?

    A45
    B50
    C60
    D30
  • Question 3 - Select One

    A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?

    A48 days
    B88 days
    C30 days
    D40 days