Two men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take to finish the job, if they start working together?
15 days
20 days
22.5 days
25 days
To solve the problem step by step, we will follow these steps:
Step 1: Understand the Efficiency of A and B
Given that A is thrice as good as B, we can denote the efficiencies of A and B as follows:
- Efficiency of A = 3 units of work/day
- Efficiency of B = 1 unit of work/day
Step 2: Establish the Relationship Between Time and Efficiency
Since time taken to complete a job is inversely proportional to efficiency, we can denote the time taken by A and B to complete the job as:
- Let the time taken by B be tB days.
- Then the time taken by A will be tA=tB−60 days (since A takes 60 days less than B).
Step 3: Set Up the Equation Based on Efficiency
From the efficiency, we know:
- Efficiency=Total WorkTime
Thus, we can write:
- For A: Total Work=3×tA
- For B: Total Work=1×tB
Since both expressions represent the same total work, we can equate them:
3(tB−60)=tB
Step 4: Solve the Equation
Now, we solve for tB:
1. Expand the equation:
3tB−180=tB
2. Rearranging gives:
3tB−tB=180
2tB=180
3. Dividing both sides by 2:
tB=90 days
Step 5: Find the Time Taken by A
Now that we have tB, we can find tA:
tA=tB−60=90−60=30 days
Step 6: Calculate the Total Work
Now we can calculate the total work done:
Using B's time:
Total Work=1×tB=1×90=90 units
Step 7: Calculate the Time Taken When A and B Work Together
When A and B work together, their combined efficiency is:
Combined Efficiency=3+1=4 units/day
To find the time taken to complete the total work together:
Time=Total WorkCombined Efficiency=904=22.5 days
Final Answer
Thus, the time taken by A and B to finish the job together is 22.5 days.
---
Given that A is thrice as good as B, we can denote the efficiencies of A and B as follows:
- Efficiency of A = 3 units of work/day
- Efficiency of B = 1 unit of work/day
Since time taken to complete a job is inversely proportional to efficiency, we can denote the time taken by A and B to complete the job as:
- Let the time taken by B be tB days.
- Then the time taken by A will be tA=tB−60 days (since A takes 60 days less than B).
From the efficiency, we know:
- Efficiency=Total WorkTime
- For A: Total Work=3×tA
- For B: Total Work=1×tB
3(tB−60)=tB
Now, we solve for tB:
1. Expand the equation:
3tB−180=tB
2. Rearranging gives:
3tB−tB=180
2tB=180
3. Dividing both sides by 2:
tB=90 days
Now that we have tB, we can find tA:
tA=tB−60=90−60=30 days
Now we can calculate the total work done:
Using B's time:
Total Work=1×tB=1×90=90 units
When A and B work together, their combined efficiency is:
Combined Efficiency=3+1=4 units/day
Time=Total WorkCombined Efficiency=904=22.5 days
Thus, the time taken by A and B to finish the job together is 22.5 days.
Similar Questions
A is twice as good a workman as B and is therefore able to finish a piece of work in 30 days less than B. In how many days they can complete the whole work, working together?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View Solution
Knowledge Check
A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
A1014B1134C1114D1113A is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?
A20B30C5D15Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
A6 daysB18 daysC5 daysD12 days
A man can do a job in 15 days. His father takes 20 days and his son finishes it in 25 days. How long will they take to complete the job if they all work together?
View SolutionA is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in
View SolutionA man completes 49 of a job in 12 days. At this rate, how many more days will it take him to finish the job ?
View SolutionA man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job?
View SolutionA is thrice as good a workman as B and is, therefore, able to finish a piece of work in 60 days less than B. The time (in days) in which they can do it working together is
View Solution