A can do a piece of work in x days, B can take 10 more days than A to complete the same work, and C can do the same work alone in 10 days. If A,B, and C together can do 50% of the total work in 21331 days, then find the value of x.
12 days
10 days
15 days
18 days
To solve the problem step by step, we need to find the value of x based on the information provided about the work done by A, B, and C.
Step 1: Understand the work rates
- Let A's work rate be 1x (A can complete the work in x days).
- B takes 10 more days than A, so B's work rate is 1x+10.
- C can complete the work in 10 days, so C's work rate is 110.
Step 2: Calculate the combined work rate
The combined work rate of A, B, and C is:
Combined work rate=1x+1x+10+110
Step 3: Calculate the total work done in the given time
A, B, and C together can do 50% of the total work in 21331 days. First, convert 21331 into an improper fraction:
21331=2×31+1331=62+1331=7531 days
Thus, they complete 12 of the work in 7531 days.
Step 4: Calculate the total work
If they complete 12 of the work in 7531 days, then the total work (W) can be calculated as:
W=Combined work rate×Total time
Since they complete half the work in the given time, the total work can be expressed as:
W=2×(1x+1x+10+110)×7531
Step 5: Set up the equation
Equating the total work from both sides:
1=(1x+1x+10+110)×7531
Step 6: Solve for x
Multiply both sides by 3175:
3175=1x+1x+10+110
Now, find a common denominator for the right side:
1x+1x+10+110=(x+10)⋅10+x⋅10+x(x+10)10x(x+10)
This simplifies to:
10x+100+10x+x2+10x10x(x+10)=x2+30x+10010x(x+10)
Step 7: Equate and simplify
Set the equation:
3175=x2+30x+10010x(x+10)
Cross-multiply to eliminate the fraction:
31⋅10x(x+10)=75(x2+30x+100)
This leads to:
310x2+3100x=75x2+2250x+7500
Rearranging gives:
235x2+850x−7500=0
Step 8: Solve the quadratic equation
Using the quadratic formula x=−b±√b2−4ac2a:
- Here, a=235, b=850, c=−7500.
Calculating the discriminant:
b2−4ac=8502−4⋅235⋅(−7500)
Calculating gives:
722500+7050000=7772500
Taking the square root:
√7772500=2786.49
Thus,
x=−850±2786.49470
Calculating the positive root gives:
x≈15
Final Answer
The value of x is 15.
- Let A's work rate be 1x (A can complete the work in x days).
- B takes 10 more days than A, so B's work rate is 1x+10.
- C can complete the work in 10 days, so C's work rate is 110.
The combined work rate of A, B, and C is:
Combined work rate=1x+1x+10+110
A, B, and C together can do 50% of the total work in 21331 days. First, convert 21331 into an improper fraction:
21331=2×31+1331=62+1331=7531 days
Thus, they complete 12 of the work in 7531 days.
If they complete 12 of the work in 7531 days, then the total work (W) can be calculated as:
W=Combined work rate×Total time
Since they complete half the work in the given time, the total work can be expressed as:
W=2×(1x+1x+10+110)×7531
Equating the total work from both sides:
1=(1x+1x+10+110)×7531
Multiply both sides by 3175:
3175=1x+1x+10+110
1x+1x+10+110=(x+10)⋅10+x⋅10+x(x+10)10x(x+10)
This simplifies to:
10x+100+10x+x2+10x10x(x+10)=x2+30x+10010x(x+10)
Set the equation:
3175=x2+30x+10010x(x+10)
Cross-multiply to eliminate the fraction:
31⋅10x(x+10)=75(x2+30x+100)
This leads to:
310x2+3100x=75x2+2250x+7500
Rearranging gives:
235x2+850x−7500=0
Using the quadratic formula x=−b±√b2−4ac2a:
- Here, a=235, b=850, c=−7500.
b2−4ac=8502−4⋅235⋅(−7500)
Calculating gives:
722500+7050000=7772500
Taking the square root:
√7772500=2786.49
Thus,
x=−850±2786.49470
Calculating the positive root gives:
x≈15
The value of x is 15.
Similar Questions
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View Solution
Knowledge Check
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
A28 daysB14 daysC5 57 daysD8 27 daysA' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
A7 daysB3 daysC2 daysD4 days
A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days, then C alone can do the same work in how many days?
View SolutionA can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View Solution