A and B can do a piece of work together in 9 days while A alone can do it in 15 days. They start working together but B leaves 3 days before the completion of the work. For how many days did A and B work together?
A)7.2
B)7.5
C)8.1
D)8
7.2
7.5
8.1
8
The correct Answer is:A
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how long they worked together before B left.
Step 1: Determine the work rates of A and B
- A can complete the work in 15 days. Therefore, A's work rate is:
Work rate of A=115 (work per day)
- A and B together can complete the work in 9 days. Therefore, their combined work rate is:
Work rate of A and B=19 (work per day)
Step 2: Calculate B's work rate
- Since A's work rate is 115 and A and B's combined work rate is 19, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=19−115
- To perform this subtraction, we need a common denominator, which is 45:
19=545,115=345
Work rate of B=545−345=245 (work per day)
Step 3: Calculate the total work
- The total work can be calculated using A's work rate:
Total work=Work rate of A×Total days A works alone=15 (days)×1 (unit of work)=1 unit of work
Step 4: Determine how much work is left when B leaves
- B leaves 3 days before the work is completed. Let's denote the total time taken to complete the work as T. Therefore, A and B worked together for T−3 days.
- The total work done by A and B together in T−3 days is:
Work done by A and B=(T−3)×(19)
- The work done by A alone in the remaining 3 days is:
Work done by A=3×(115)
Step 5: Set up the equation for total work
- The total work equation is:
(T−3)×(19)+3×(115)=1
Step 6: Solve the equation
- Substituting the values:
T−39+315=1
- Simplifying 315 to 15:
T−39+15=1
- Finding a common denominator (45):
5(T−3)45+945=1
5T−15+945=1
5T−6=45
5T=51⟹T=515=10.2 days
Step 7: Calculate how many days A and B worked together
- Since B left 3 days before the work was completed:
Days A and B worked together=T−3=10.2−3=7.2 days
Final Answer
Thus, A and B worked together for 7.2 days.
- A can complete the work in 15 days. Therefore, A's work rate is:
Work rate of A=115 (work per day)
Work rate of A and B=19 (work per day)
- Since A's work rate is 115 and A and B's combined work rate is 19, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=19−115
19=545,115=345
Work rate of B=545−345=245 (work per day)
- The total work can be calculated using A's work rate:
Total work=Work rate of A×Total days A works alone=15 (days)×1 (unit of work)=1 unit of work
- B leaves 3 days before the work is completed. Let's denote the total time taken to complete the work as T. Therefore, A and B worked together for T−3 days.
- The total work done by A and B together in T−3 days is:
Work done by A and B=(T−3)×(19)
Work done by A=3×(115)
- The total work equation is:
(T−3)×(19)+3×(115)=1
- Substituting the values:
T−39+315=1
- Simplifying 315 to 15:
T−39+15=1
5(T−3)45+945=1
5T−15+945=1
5T−6=45
5T=51⟹T=515=10.2 days
- Since B left 3 days before the work was completed:
Days A and B worked together=T−3=10.2−3=7.2 days
Thus, A and B worked together for 7.2 days.
Similar Questions
A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
View SolutionA can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?
View Solution
Knowledge Check
A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
A10B12C9D11A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
A10B13.75C12.5D11.25A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2
A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :
View SolutionA can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312
View Solution