A and B can do a piece of work together in 9 days while A alone can do it in 15 days. They start working together but B leaves 3 days before the completion of the work. For how many days did A and B work together?
A)7.2
B)7.5
C)8.1
D)8

A

7.2

B

7.5

C

8.1

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the work rates of A and B, then calculate how long they worked together before B left.

Step 1: Determine the work rates of A and B
- A can complete the work in 15 days. Therefore, A's work rate is:
Work rate of A=115 (work per day)

- A and B together can complete the work in 9 days. Therefore, their combined work rate is:
Work rate of A and B=19 (work per day)

Step 2: Calculate B's work rate
- Since A's work rate is 115 and A and B's combined work rate is 19, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=Work rate of A and BWork rate of A
Work rate of B=19115

- To perform this subtraction, we need a common denominator, which is 45:
19=545,115=345
Work rate of B=545345=245 (work per day)

Step 3: Calculate the total work
- The total work can be calculated using A's work rate:
Total work=Work rate of A×Total days A works alone=15 (days)×1 (unit of work)=1 unit of work

Step 4: Determine how much work is left when B leaves
- B leaves 3 days before the work is completed. Let's denote the total time taken to complete the work as T. Therefore, A and B worked together for T3 days.

- The total work done by A and B together in T3 days is:
Work done by A and B=(T3)×(19)

- The work done by A alone in the remaining 3 days is:
Work done by A=3×(115)

Step 5: Set up the equation for total work
- The total work equation is:
(T3)×(19)+3×(115)=1

Step 6: Solve the equation
- Substituting the values:
T39+315=1
- Simplifying 315 to 15:
T39+15=1

- Finding a common denominator (45):
5(T3)45+945=1
5T15+945=1
5T6=45
5T=51T=515=10.2 days

Step 7: Calculate how many days A and B worked together
- Since B left 3 days before the work was completed:
Days A and B worked together=T3=10.23=7.2 days

Final Answer
Thus, A and B worked together for 7.2 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

    A10
    B12
    C9
    D11
  • A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

    A10
    B13.75
    C12.5
    D11.25
  • A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

    A6
    B5
    C7
    D7.2