A contractor takes a contract to complete a road in 60 days and employs 70 labours. After 25 days, he found that one fourth work is completed. How many more labours he requires to complete the remaining work in time?
90
80
85
82
The correct Answer is:B
Step by step video, text & image solution for A contractor takes a contract to complete a road in 60 days and employs 70 labours. After 25 days, he found that one fourth work is completed. How many more labours he requires to complete the remaining work in time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Similar Questions
A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third work is completed. How many more labours he requires to complete the remaining work in time?
एक ठेकेदार 60 दिनों में एक सड़क को पूरा करने का ठेका लेता है और 105 मजदूरों को इस कार्य में लगाता है। 25 दिनों के बाद, एक तिहाई काम पूरा हो जाता है। शेष काम को समय पर पूरा करने के लिए उसे कितने और मजदूरों की आवश्यकता पड़ेगी?
View Solution15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers
View Solution
Knowledge Check
20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?
A8B10C15D2020 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?
AA) 8BB) 10CC) 15DD) 20A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?
Aa) 25Bb) 30Cc) 35Dd) 20
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution