Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

A

3/5

B

1/3

C

1/2

D

2/5

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to determine how much work Vikram and Vivek have completed together in the 20 days they worked.

Step 1: Determine the work rate of Vikram and Vivek together.
Since Vikram and Vivek can finish the work in 50 days, we can say that their combined work rate is:
Work Rate=1 (complete work)50 days=150 work/day

Step 2: Calculate the total work done in 20 days.
Now, if they worked together for 20 days, the amount of work they completed in that time can be calculated as:
Work Done=Work Rate×Number of Days Worked=150×20

Step 3: Perform the multiplication.
Calculating this gives:
Work Done=2050=25

Step 4: Conclusion
Thus, the total work done by Vikram and Vivek together in 20 days is 25 of the entire work.

Final Answer:
The amount of work done by them is 25.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left

    A3/5
    B1/3
    C1/2
    D2/5
  • A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?

    A50 days
    B60 days
    C48 days
    D54 days
  • A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…

    A48 days
    B50 days
    C54 days
    D60 days