Doubtnut Promotions Sticky

If 'A' is 6 times more efficient than 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together.

A

A)2 days

B

B)4 days

C

C)6 days

D

D)8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for If 'A' is 6 times more efficient than 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

    A4
    B2
    C12
    D16
  • Question 1 - Select One

    A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.

    A9 days
    B12 days
    C18 days
    D24 days
  • Question 1 - Select One

    If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
    (a)60 days
    (b) 50 days
    (c)30 days
    (d)40 days

    A60 days
    B50 days
    C30 days
    D40 days
  • Question 1 - Select One

    A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is

    A16
    B8
    C12
    D24
  • Question 1 - Select One

    A is three times more efficient than B hence he takes 60 days less days taken by B in a certain task In how many days will both complete this work?

    A30 days
    B45 days
    C175 days
    D22.5 days
  • Question 1 - Select One

    A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

    A36
    B18
    C48
    D30
  • Question 1 - Select One

    B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.

    A11 days
    B44 days
    C33 days
    D30 days
  • Question 1 - Select One

    A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • Question 1 - Select One

    A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?

    A4
    B2
    C12
    D16

Similar Questions