If 'A' is 6 times more efficient than 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together.
A
A)2 days
B
B)4 days
C
C)6 days
D
D)8 days
Video Solution
Text Solution
The correct Answer is:B
|
Answer
Step by step video, text & image solution for If 'A' is 6 times more efficient than 'B', 'B' takes 32 days to complete the task, then find the number of days required to finish the whole work by 'A' and 'B' working together. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Knowledge Check
- Question 1 - Select One
A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?
A4B2C12D16 - Question 1 - Select One
A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
A9 daysB12 daysC18 daysD24 days - Question 1 - Select One
If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 daysA60 daysB50 daysC30 daysD40 days - Question 1 - Select One
A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is
A16B8C12D24 - Question 1 - Select One
A is three times more efficient than B hence he takes 60 days less days taken by B in a certain task In how many days will both complete this work?
A30 daysB45 daysC175 daysD22.5 days - Question 1 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30 - Question 1 - Select One
B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.
A11 daysB44 daysC33 daysD30 days - Question 1 - Select One
A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
A11516B21516C31516D41516 - Question 1 - Select One
A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
A4B2C12D16