Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil Ieft. If Rohit worked alone for 3 days, find the total number of days he took to complete the whole work.
A. 31/5
B. 51/5
C. 21/5
D. 13/5
D
B
C
A
The correct Answer is:B
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work done by Anil and Rohit
Anil can complete the work in 14 days, and Rohit can complete it in 21 days. To find their efficiencies, we can calculate the amount of work they can do in one day.
- Total work can be considered as the least common multiple (LCM) of 14 and 21, which is 42 units.
- Anil's efficiency = Total work / Time taken by Anil = 42 / 14 = 3 units per day.
- Rohit's efficiency = Total work / Time taken by Rohit = 42 / 21 = 2 units per day.
Step 2: Calculate combined efficiency
When Anil and Rohit work together, their combined efficiency is:
- Combined efficiency = Anil's efficiency + Rohit's efficiency = 3 + 2 = 5 units per day.
Step 3: Set up the equation for the work done
Let’s assume they worked together for X days. The work done by both of them together in X days is:
- Work done together = Combined efficiency × Days worked = 5X units.
After working together for X days, Anil leaves, and Rohit works alone for 3 days. The work done by Rohit in those 3 days is:
- Work done by Rohit alone = Rohit's efficiency × Days worked = 2 × 3 = 6 units.
Step 4: Write the equation for total work
The total work done by both Anil and Rohit together and then by Rohit alone should equal the total work:
5X+6=42
Step 5: Solve for X
Rearranging the equation:
5X=42−6
5X=36
X=365
Step 6: Calculate total days taken
Now, the total number of days taken to complete the work is the days they worked together plus the days Rohit worked alone:
Total days=X+3=365+3
Convert 3 into a fraction:
3=155
So,
Total days=365+155=515
Conclusion
The total number of days taken to complete the whole work is 515.
Final Answer
The correct option is B. 515.
Anil can complete the work in 14 days, and Rohit can complete it in 21 days. To find their efficiencies, we can calculate the amount of work they can do in one day.
- Anil's efficiency = Total work / Time taken by Anil = 42 / 14 = 3 units per day.
- Rohit's efficiency = Total work / Time taken by Rohit = 42 / 21 = 2 units per day.
When Anil and Rohit work together, their combined efficiency is:
- Combined efficiency = Anil's efficiency + Rohit's efficiency = 3 + 2 = 5 units per day.
Let’s assume they worked together for X days. The work done by both of them together in X days is:
- Work done together = Combined efficiency × Days worked = 5X units.
- Work done by Rohit alone = Rohit's efficiency × Days worked = 2 × 3 = 6 units.
The total work done by both Anil and Rohit together and then by Rohit alone should equal the total work:
5X+6=42
Rearranging the equation:
5X=42−6
5X=36
X=365
Now, the total number of days taken to complete the work is the days they worked together plus the days Rohit worked alone:
Total days=X+3=365+3
3=155
So,
Total days=365+155=515
The total number of days taken to complete the whole work is 515.
The correct option is B. 515.
Similar Questions
A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then A fell ill and B had to complete the remaining work alone. In how many days was the work completed?
View Solution
Knowledge Check
Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil Ieft. If Rohit worked alone for 3 days, find the total number of days he took to complete the whole work.
A. 31/5
B. 51/5
C. 21/5
D. 13/5ADBBCCDAA can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312
A635daysB812daysC1015daysD1312daysRaja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :
A7B8.5C5D1015
A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View SolutionA can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
View SolutionA can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?
View Solution