Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil Ieft. If Rohit worked alone for 3 days, find the total number of days he took to complete the whole work.
A. 31/5
B. 51/5
C. 21/5
D. 13/5

A

D

B

B

C

C

D

A

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by Anil and Rohit
Anil can complete the work in 14 days, and Rohit can complete it in 21 days. To find their efficiencies, we can calculate the amount of work they can do in one day.

- Total work can be considered as the least common multiple (LCM) of 14 and 21, which is 42 units.
- Anil's efficiency = Total work / Time taken by Anil = 42 / 14 = 3 units per day.
- Rohit's efficiency = Total work / Time taken by Rohit = 42 / 21 = 2 units per day.

Step 2: Calculate combined efficiency
When Anil and Rohit work together, their combined efficiency is:
- Combined efficiency = Anil's efficiency + Rohit's efficiency = 3 + 2 = 5 units per day.

Step 3: Set up the equation for the work done
Let’s assume they worked together for X days. The work done by both of them together in X days is:
- Work done together = Combined efficiency × Days worked = 5X units.

After working together for X days, Anil leaves, and Rohit works alone for 3 days. The work done by Rohit in those 3 days is:
- Work done by Rohit alone = Rohit's efficiency × Days worked = 2 × 3 = 6 units.

Step 4: Write the equation for total work
The total work done by both Anil and Rohit together and then by Rohit alone should equal the total work:
5X+6=42

Step 5: Solve for X
Rearranging the equation:
5X=426
5X=36
X=365

Step 6: Calculate total days taken
Now, the total number of days taken to complete the work is the days they worked together plus the days Rohit worked alone:
Total days=X+3=365+3

Convert 3 into a fraction:
3=155
So,
Total days=365+155=515

Conclusion
The total number of days taken to complete the whole work is 515.

Final Answer
The correct option is B. 515.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil Ieft. If Rohit worked alone for 3 days, find the total number of days he took to complete the whole work.
    A. 31/5
    B. 51/5
    C. 21/5
    D. 13/5

    AD
    BB
    CC
    DA
  • A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312

    A635days
    B812days
    C1015days
    D1312days
  • Raja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :

    A7
    B8.5
    C5
    D1015