Atul can do a piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work?
A. 12
B. 6
C. 18
D. 10

A

D

B

A

C

C

D

B

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine how much more time Atul takes compared to Aaravya to complete the same piece of work.

1. Determine Atul's Efficiency:
- Atul can complete the work in 18 days.
- We can assume Atul's efficiency (E_A) is 1 unit of work per day. Therefore, in 18 days, he completes 18 units of work.
- Thus, Atul's efficiency is EA=118 (work done per day).

2. Calculate Aaravya's Efficiency:
- Aaravya is 50% more efficient than Atul.
- If Atul's efficiency is 1 unit, then Aaravya's efficiency (E_B) is 1+0.5×1=1.5 units of work per day.
- This can also be expressed as EB=32 (work done per day).

3. Calculate the Total Work:
- The total work can be calculated based on Atul's efficiency and the time he takes.
- Total work (W) = Efficiency of Atul × Time taken by Atul
- Therefore, W=EA×18=118×18=1 (total work).

4. Calculate the Time Taken by Aaravya:
- To find out how long Aaravya takes to complete the same work, we use the formula:
- Time taken by Aaravya = Total Work / Efficiency of Aaravya
- Thus, TimeB=WEB=132=23 days.

5. Calculate the Difference in Time:
- Now, we need to find out how much more time Atul takes compared to Aaravya.
- Difference in time = Time taken by Atul - Time taken by Aaravya
- Therefore, Difference=1823.
- To perform this subtraction, convert 18 into a fraction: 18=543.
- Thus, Difference=54323=523 days.

6. Convert the Difference to Days:
- The difference in time is approximately 17.33 days, which we can round to 18 days.

Final Answer:
Atul takes 6 days more than Aaravya to complete the same piece of work.

Correct Option: B. 6

|


Similar Questions


Knowledge Check

  • A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

    A10days
    B712 days
    C12days
    D1012 days
  • A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?

    A17 days
    B18 days
    C15 days
    D12 days
  • A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

    A446 days
    B313 days
    C514 days
    D223 days