X,Y and Z take 18 dyas to complete a piece of work. If X works. If X works alone he finishes the work in 36 days and if Y works alone he finishes it in 60 days. Long will it take Z to complete the work alone ?
A. 78 days
B. 90 days
C. 96 days
D. 14 days
B
A
D
C
The correct Answer is:A
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the work done by X and Y in one day.
- X can complete the work in 36 days, so the work done by X in one day is:
Work done by X in one day=136
- Y can complete the work in 60 days, so the work done by Y in one day is:
Work done by Y in one day=160
Step 2: Let Z's time to complete the work alone be z days.
- Therefore, the work done by Z in one day is:
Work done by Z in one day=1z
Step 3: Combine the work done by X, Y, and Z together.
- Together, X, Y, and Z can complete the work in 18 days, so their combined work done in one day is:
Combined work in one day=118
Step 4: Set up the equation.
- The equation combining the work done by X, Y, and Z in one day is:
136+160+1z=118
Step 5: Solve for 1z.
- First, we need to find a common denominator for the fractions on the left side. The least common multiple (LCM) of 36, 60, and 18 is 180.
- Rewrite each fraction with a denominator of 180:
136=5180,160=3180,118=10180
- Substitute these values into the equation:
5180+3180+1z=10180
- Combine the fractions:
8180+1z=10180
Step 6: Isolate 1z.
- Subtract 8180 from both sides:
1z=10180−8180=2180
- Simplify:
1z=190
Step 7: Solve for z.
- Taking the reciprocal gives:
z=90
Conclusion:
- Therefore, Z alone can complete the work in 90 days.
Final Answer:
B. 90 days
- X can complete the work in 36 days, so the work done by X in one day is:
Work done by X in one day=136
Work done by Y in one day=160
- Therefore, the work done by Z in one day is:
Work done by Z in one day=1z
- Together, X, Y, and Z can complete the work in 18 days, so their combined work done in one day is:
Combined work in one day=118
- The equation combining the work done by X, Y, and Z in one day is:
136+160+1z=118
- First, we need to find a common denominator for the fractions on the left side. The least common multiple (LCM) of 36, 60, and 18 is 180.
- Rewrite each fraction with a denominator of 180:
136=5180,160=3180,118=10180
- Substitute these values into the equation:
5180+3180+1z=10180
- Combine the fractions:
8180+1z=10180
- Subtract 8180 from both sides:
1z=10180−8180=2180
- Simplify:
1z=190
- Taking the reciprocal gives:
z=90
- Therefore, Z alone can complete the work in 90 days.
B. 90 days
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View Solution
Knowledge Check
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 daysA man, a woman and a boy can together complete a piece of work In 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman alone take to complete the work?
A9 daysB21 daysC24 daysD27 daysX can do a piece of work in 40 days. He works it for 8 days and then Y finished it in 16 days How long will they together take to complete the work?
A1313 daysB15 daysC20 daysD56 days
X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work?
View SolutionA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
View SolutionAtul and Binay together complete a piece of work in 5 days. If Binay alone can complete the same work in 8 days, how many days can Atul take to complete the same work alone?
A. 40/3 days
B. 20/3 days
C. 9 days
D. 10 days
View SolutionP can do a piece of work in 12 days , while Q alone can finish it in 8 days . With the help of R , they can finish the work in 4 days. How long willRtake to finish the work alone?
View SolutionA man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone ?
View Solution