A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
10 days / 10 दिन
4 days / 4 दिन
6 days / 6 दिन
8 days / 8 दिन
The correct Answer is:C
Ae+Be=13
∴2(Ae+Be)=23
शेष कार्य =1−23=13
∵13 कार्य पूरा करता है A 2 दिन में
∴1 कार्य पूरा करता है A2×3 दिन में
= 6 दिन में
i.e. Ae=16
∵Ae+Be=13
⇒16+Be=13⇒Be=13−16=2−16=16
अतः B अकेले उस कार्य को दिनों में 6 पूरा करेगा।
Similar Questions
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View SolutionA can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View SolutionA, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days A left. Then B and C completed the work in 10 more days. A alone could complete the work in : a. 15 days b. 16 days c. 25 days d. 50 days
View Solution