X and Y can do a piece of work in 10 days, Y and Z in 12 days and Z and X in 15 days. In how many days can Z alone do the work?

A

40

B

24

C

18

D

36

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will use the information provided about the work done by X, Y, and Z together.

Step 1: Determine the total work done
We know:
- X and Y can complete the work in 10 days.
- Y and Z can complete the work in 12 days.
- Z and X can complete the work in 15 days.

To find the total work, we can take the least common multiple (LCM) of the days taken by each pair to complete the work.

The LCM of 10, 12, and 15 is 60. This means we can assume the total work is 60 units.

Step 2: Calculate the efficiencies of each pair
Now we can calculate the efficiencies of each pair:
- Efficiency of X and Y:
Efficiency of (X + Y)=60 units10 days=6 units/day

- Efficiency of Y and Z:
Efficiency of (Y + Z)=60 units12 days=5 units/day

- Efficiency of Z and X:
Efficiency of (Z + X)=60 units15 days=4 units/day

Step 3: Set up equations for individual efficiencies
Let the efficiencies of X, Y, and Z be represented as x, y, and z respectively. We can set up the following equations based on the efficiencies calculated:

1. x+y=6 (from X and Y)
2. y+z=5 (from Y and Z)
3. z+x=4 (from Z and X)

Step 4: Solve the equations
Now we can solve these equations step by step.

From equation (1):
y=6x(4)

Substituting equation (4) into equation (2):
(6x)+z=5
z=56+x=x1(5)

Now substituting equation (5) into equation (3):
(x1)+x=4
2x1=4
2x=5x=52=2.5 units/day

Now substituting x back into equation (4) to find y:
y=62.5=3.5 units/day

Substituting x into equation (5) to find z:
z=2.51=1.5 units/day

Step 5: Calculate the time taken by Z alone
Now that we have the efficiency of Z, we can calculate how long it will take Z to complete the total work of 60 units.

Using the formula:
Time=Total WorkEfficiency of Z=601.5=40 days

Final Answer
Z alone can complete the work in 40 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?

    A30,20,50
    B30,45,60
    C30,20,60
    D20,30,50
  • Question 2 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?

    A60
    B50
    C25
    D24
  • Question 3 - Select One

    A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?

    A6
    B4
    C5
    D10