A and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.

A

36 days

B

48 days

C

96 days

D

80 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by A, B, and C together and then isolate A's work.

Step 1: Calculate the work done by A and B together.
A and B together can complete the work in 16 days. Therefore, their combined work rate is:
Work rate of A and B=116 (work per day)

Step 2: Calculate the work done by B and C together.
B and C together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of B and C=112 (work per day)

Step 3: Calculate the work done by A and C together.
A and C together can complete the work in 24 days. Therefore, their combined work rate is:
Work rate of A and C=124 (work per day)

Step 4: Set up the equations for total work rates.
Let the work rates of A, B, and C be a, b, and c respectively. We can write the following equations based on the work rates:
1. a+b=116 (Equation 1)
2. b+c=112 (Equation 2)
3. a+c=124 (Equation 3)

Step 5: Add all three equations.
Adding all three equations gives:
(a+b)+(b+c)+(a+c)=116+112+124
This simplifies to:
2a+2b+2c=116+112+124

Step 6: Find a common denominator and simplify.
The least common multiple of 16, 12, and 24 is 48. So, we convert each fraction:
116=348,112=448,124=248
Adding these gives:
348+448+248=948
Thus, we have:
2a+2b+2c=948
Dividing by 2:
a+b+c=996

Step 7: Isolate A's work rate.
Now, we can find A's work rate by subtracting the work rates of B and C from the total:
1. From Equation 2, we know b+c=112=448=896.
2. Thus, we can find A's work rate:
a=(a+b+c)(b+c)=996896=196

Step 8: Calculate the number of days A will take to complete the work alone.
Since A's work rate is 196, it means A can complete the work alone in:
Days taken by A=1196=96 days

Final Answer:
A will take 96 days to complete the work alone.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

    A80 days
    B100 days
    C120 days
    D150 days
  • A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
    (a)12 days
    (b)14 days
    (c)16 days
    (d)18 days

    A12 days
    B14 days
    C16 days
    D18 days
  • A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A12013 days
    B48013 days
    C24013 days
    D96013 days