A can do work in 18 days. he work at it for 12 days and B finished the remaining work in 8 days. Balon can finish the work in
16 days
24 days
35 days
28 days
The correct Answer is:B
To solve the problem step by step, we need to determine how long Balon can finish the work given the information about A and B.
Step 1: Determine A's Work Rate
A can complete the work in 18 days. Therefore, A's work rate is:
Work rate of A=118 (work per day)
Step 2: Calculate Work Done by A in 12 Days
A works for 12 days. The amount of work done by A in this time is:
Work done by A=12×118=1218=23
Step 3: Determine Remaining Work
The total work is considered as 1 (whole work). The remaining work after A has worked for 12 days is:
Remaining work=1−23=13
Step 4: Determine B's Work Rate
Let’s denote B's work rate as 1b where b is the number of days B takes to complete the work alone. We know from the problem that B finishes the remaining work in 8 days. Therefore, the work done by B in 8 days is:
Work done by B=8×1b
Since B completes the remaining 13 of the work, we can set up the equation:
8×1b=13
Step 5: Solve for B's Work Rate
Now we can solve for b:
8b=13
Cross-multiplying gives:
8⋅3=1⋅b⟹b=24
Conclusion
Thus, B can finish the work alone in 24 days.
Summary of Steps:
1. Calculate A's work rate.
2. Find the work done by A in 12 days.
3. Determine the remaining work.
4. Set up the equation for B's work rate based on the remaining work.
5. Solve for B's total time to finish the work.
A can complete the work in 18 days. Therefore, A's work rate is:
Work rate of A=118 (work per day)
A works for 12 days. The amount of work done by A in this time is:
Work done by A=12×118=1218=23
The total work is considered as 1 (whole work). The remaining work after A has worked for 12 days is:
Remaining work=1−23=13
Let’s denote B's work rate as 1b where b is the number of days B takes to complete the work alone. We know from the problem that B finishes the remaining work in 8 days. Therefore, the work done by B in 8 days is:
Work done by B=8×1b
Since B completes the remaining 13 of the work, we can set up the equation:
8×1b=13
Now we can solve for b:
8b=13
Cross-multiplying gives:
8⋅3=1⋅b⟹b=24
Thus, B can finish the work alone in 24 days.
1. Calculate A's work rate.
2. Find the work done by A in 12 days.
3. Determine the remaining work.
4. Set up the equation for B's work rate based on the remaining work.
5. Solve for B's total time to finish the work.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View Solution
Knowledge Check
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
A16 daysB24 daysC28 daysD29 daysA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
A24 daysB25 daysC30 daysD32 days
Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
View SolutionA can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
View SolutionA and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution