A can do work in 18 days. he work at it for 12 days and B finished the remaining work in 8 days. Balon can finish the work in

A

16 days

B

24 days

C

35 days

D

28 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to determine how long Balon can finish the work given the information about A and B.

Step 1: Determine A's Work Rate
A can complete the work in 18 days. Therefore, A's work rate is:
Work rate of A=118 (work per day)

Step 2: Calculate Work Done by A in 12 Days
A works for 12 days. The amount of work done by A in this time is:
Work done by A=12×118=1218=23

Step 3: Determine Remaining Work
The total work is considered as 1 (whole work). The remaining work after A has worked for 12 days is:
Remaining work=123=13

Step 4: Determine B's Work Rate
Let’s denote B's work rate as 1b where b is the number of days B takes to complete the work alone. We know from the problem that B finishes the remaining work in 8 days. Therefore, the work done by B in 8 days is:
Work done by B=8×1b
Since B completes the remaining 13 of the work, we can set up the equation:
8×1b=13

Step 5: Solve for B's Work Rate
Now we can solve for b:
8b=13
Cross-multiplying gives:
83=1bb=24

Conclusion
Thus, B can finish the work alone in 24 days.

Summary of Steps:
1. Calculate A's work rate.
2. Find the work done by A in 12 days.
3. Determine the remaining work.
4. Set up the equation for B's work rate based on the remaining work.
5. Solve for B's total time to finish the work.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

    A16 days
    B24 days
    C28 days
    D29 days
  • A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70
  • A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in

    A24 days
    B25 days
    C30 days
    D32 days