The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
4 Days
3 Days
2 Days
1 Days
To solve the problem, we need to find out how long it will take for 12 men, 10 children, and 8 women to complete a job, given that a child can finish the job in 20 days.
1. Determine the total work done by a child:
- A child can finish the job in 20 days.
- Therefore, the total work can be considered as 1000 units (for simplicity).
- Work done by one child in one day = Total work / Number of days = 1000 units / 20 days = 50 units/day.
2. Calculate the work done by 5 children in one day:
- Work done by 5 children in one day = 5 * Work done by one child = 5 * 50 units/day = 250 units/day.
3. Relate the work done by men and children:
- We know that the time taken by 4 men is double the time taken by 5 children.
- If 5 children do 250 units in one day, then 4 men must do the same work in half the time.
- Therefore, work done by 4 men in one day = 250 units/day.
4. Calculate the work done by one man in one day:
- Work done by one man = Total work done by 4 men / 4 = 250 units/day / 4 = 62.5 units/day.
5. Determine the work done by women:
- Each man is twice as fast as a woman.
- Therefore, work done by one woman = Work done by one man / 2 = 62.5 units/day / 2 = 31.25 units/day.
6. Calculate the total work done by 12 men, 10 children, and 8 women in one day:
- Work done by 12 men = 12 * 62.5 units/day = 750 units/day.
- Work done by 10 children = 10 * 50 units/day = 500 units/day.
- Work done by 8 women = 8 * 31.25 units/day = 250 units/day.
7. Total work done in one day by all:
- Total work done = Work done by 12 men + Work done by 10 children + Work done by 8 women
- Total work done = 750 units/day + 500 units/day + 250 units/day = 1500 units/day.
8. Determine the time taken to complete the job:
- Since the total work is 1000 units and they can do 1500 units in one day, the time taken to complete the job = Total work / Total work done in one day = 1000 units / 1500 units/day = 2/3 days.
Final Answer:
The time taken by 12 men, 10 children, and 8 women to complete the job is 2/3 of a day.
- A child can finish the job in 20 days.
- Therefore, the total work can be considered as 1000 units (for simplicity).
- Work done by one child in one day = Total work / Number of days = 1000 units / 20 days = 50 units/day.
- Work done by 5 children in one day = 5 * Work done by one child = 5 * 50 units/day = 250 units/day.
- We know that the time taken by 4 men is double the time taken by 5 children.
- If 5 children do 250 units in one day, then 4 men must do the same work in half the time.
- Therefore, work done by 4 men in one day = 250 units/day.
- Work done by one man = Total work done by 4 men / 4 = 250 units/day / 4 = 62.5 units/day.
- Each man is twice as fast as a woman.
- Therefore, work done by one woman = Work done by one man / 2 = 62.5 units/day / 2 = 31.25 units/day.
- Work done by 12 men = 12 * 62.5 units/day = 750 units/day.
- Work done by 10 children = 10 * 50 units/day = 500 units/day.
- Work done by 8 women = 8 * 31.25 units/day = 250 units/day.
- Total work done = Work done by 12 men + Work done by 10 children + Work done by 8 women
- Total work done = 750 units/day + 500 units/day + 250 units/day = 1500 units/day.
- Since the total work is 1000 units and they can do 1500 units in one day, the time taken to complete the job = Total work / Total work done in one day = 1000 units / 1500 units/day = 2/3 days.
The time taken by 12 men, 10 children, and 8 women to complete the job is 2/3 of a day.
Topper's Solved these Questions
Similar Questions
Knowledge Check
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
A2 daysB218 daysC4 daysD1 day12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?
A2 hrsB3.2 hrsC3 .5 hrsD3 hrs24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
A30B40C25D50
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
View Solution22 men can complete a job in 16days. In how many days, will 32 men complete that job?
View Solution12 men and 16 women can complete a jon in 5 days. 13 men and 24 women can complete the same job in 4 days. How long, in days, will 5 men and 10 women take to complete the same job?
View Solution
