Satish is 50% more efficient than Charan. They together
start the work and 712 th of work is left after 8 days. Find in
what time Charan alone will complete the whole work.
36 days
44 days
50 days
48 days
The correct Answer is:(d)
Ratio of efficiency of Satish to charan is 3:2
Let, In 8 days they copmplete =(3+2)×8=40 units
So, total work =40×125 units
Time taken by Charan alone to complete whole work
=40×125×2=48 days
Topper's Solved these Questions
Similar Questions
Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View SolutionAnand is 50% more efficient than Bharath and Bharath is 100% more efficient that Chandu. Working together, they can complete a work in 10 days. In how many days can Anand alone do the work?
View Solution
Knowledge Check
A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 daysA can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 daysA is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% that work?
A9B7C10D8
A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% of that work?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionP,Q and R together can complete 50% of a work in 2 days. All three start the work but after two days Q. left. P and R alone in 8 days. In how many days can P alone complete the work?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View Solution