Shahu can do a work in 18 days, Yash can do the same work
in 24 days and Dixit can do the whole work in 36 days. If
Shahu & Yash work for first A days together after that Dixit
also joined them, remaining work is completed in (A+445)
days. Find for how many days all three worked together?

A

645days

B

545days

C

445days

D

845days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(d)


To solve the problem step by step, we will first determine the work efficiency of each person, then calculate the total work done, and finally find out how many days all three worked together.

Step 1: Calculate the work efficiency of each person
- Shahu can complete the work in 18 days. Therefore, his work efficiency is:
Efficiency of Shahu=118 (work per day)

- Yash can complete the work in 24 days. Therefore, his work efficiency is:
Efficiency of Yash=124 (work per day)

- Dixit can complete the work in 36 days. Therefore, his work efficiency is:
Efficiency of Dixit=136 (work per day)

Step 2: Find the combined efficiency of Shahu and Yash
When Shahu and Yash work together, their combined efficiency is:
Combined efficiency of Shahu and Yash=118+124
To add these fractions, we need a common denominator. The LCM of 18 and 24 is 72.
118=472,124=372
Thus,
Combined efficiency=472+372=772 (work per day)

Step 3: Calculate the work done by Shahu and Yash in A days
If Shahu and Yash work together for A days, the total work done by them is:
Work done by Shahu and Yash in A days=Combined efficiency×A=772×A

Step 4: Calculate the remaining work after A days
The total work is considered as 1 unit. Therefore, the remaining work after A days is:
Remaining work=1772×A

Step 5: Calculate the combined efficiency of all three working together
When all three work together, their combined efficiency is:
Combined efficiency of Shahu, Yash, and Dixit=118+124+136
Finding a common denominator (LCM of 18, 24, and 36 is 72):
118=472,124=372,136=272
Thus,
Combined efficiency=472+372+272=972=18 (work per day)

Step 6: Calculate the time taken to complete the remaining work
The remaining work is completed in A+445 days, which can be converted to an improper fraction:
445=245A+445=A+245=5A+245
The work done in this time is:
Work done by all three=Combined efficiency×Time=18×5A+245

Step 7: Set up the equation
The remaining work can be expressed as:
1772A=18×5A+245

Step 8: Solve the equation
Cross-multiplying gives:
(1772A)×40=5A+24
Expanding and simplifying:
4028072A=5A+24
Multiplying through by 72 to eliminate the fraction:
2880280A=360A+1728
Combining like terms:
28801728=360A+280A
1152=640AA=1152640=3620=95=1.8

Step 9: Calculate the total days all three worked together
Now substituting A back into the time they worked together:
A+445=95+245=335=6.6 days

Final Answer
Thus, the total number of days all three worked together is:
Total days=6.6 days

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?

    A24 days
    B18 days
    C20 days
    D16 days
  • A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?

    A12
    B10
    C15
    D24
  • A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12