Shahu can do a work in 18 days, Yash can do the same work
in 24 days and Dixit can do the whole work in 36 days. If
Shahu & Yash work for first A days together after that Dixit
also joined them, remaining work is completed in (A+445)
days. Find for how many days all three worked together?
645days
545days
445days
845days
The correct Answer is:(d)
To solve the problem step by step, we will first determine the work efficiency of each person, then calculate the total work done, and finally find out how many days all three worked together.
Step 1: Calculate the work efficiency of each person
- Shahu can complete the work in 18 days. Therefore, his work efficiency is:
Efficiency of Shahu=118 (work per day)
- Yash can complete the work in 24 days. Therefore, his work efficiency is:
Efficiency of Yash=124 (work per day)
- Dixit can complete the work in 36 days. Therefore, his work efficiency is:
Efficiency of Dixit=136 (work per day)
Step 2: Find the combined efficiency of Shahu and Yash
When Shahu and Yash work together, their combined efficiency is:
Combined efficiency of Shahu and Yash=118+124
To add these fractions, we need a common denominator. The LCM of 18 and 24 is 72.
118=472,124=372
Thus,
Combined efficiency=472+372=772 (work per day)
Step 3: Calculate the work done by Shahu and Yash in A days
If Shahu and Yash work together for A days, the total work done by them is:
Work done by Shahu and Yash in A days=Combined efficiency×A=772×A
Step 4: Calculate the remaining work after A days
The total work is considered as 1 unit. Therefore, the remaining work after A days is:
Remaining work=1−772×A
Step 5: Calculate the combined efficiency of all three working together
When all three work together, their combined efficiency is:
Combined efficiency of Shahu, Yash, and Dixit=118+124+136
Finding a common denominator (LCM of 18, 24, and 36 is 72):
118=472,124=372,136=272
Thus,
Combined efficiency=472+372+272=972=18 (work per day)
Step 6: Calculate the time taken to complete the remaining work
The remaining work is completed in A+445 days, which can be converted to an improper fraction:
445=245⟹A+445=A+245=5A+245
The work done in this time is:
Work done by all three=Combined efficiency×Time=18×5A+245
Step 7: Set up the equation
The remaining work can be expressed as:
1−772A=18×5A+245
Step 8: Solve the equation
Cross-multiplying gives:
(1−772A)×40=5A+24
Expanding and simplifying:
40−28072A=5A+24
Multiplying through by 72 to eliminate the fraction:
2880−280A=360A+1728
Combining like terms:
2880−1728=360A+280A
1152=640A⟹A=1152640=3620=95=1.8
Step 9: Calculate the total days all three worked together
Now substituting A back into the time they worked together:
A+445=95+245=335=6.6 days
Final Answer
Thus, the total number of days all three worked together is:
Total days=6.6 days
- Shahu can complete the work in 18 days. Therefore, his work efficiency is:
Efficiency of Shahu=118 (work per day)
Efficiency of Yash=124 (work per day)
Efficiency of Dixit=136 (work per day)
When Shahu and Yash work together, their combined efficiency is:
Combined efficiency of Shahu and Yash=118+124
To add these fractions, we need a common denominator. The LCM of 18 and 24 is 72.
118=472,124=372
Thus,
Combined efficiency=472+372=772 (work per day)
If Shahu and Yash work together for A days, the total work done by them is:
Work done by Shahu and Yash in A days=Combined efficiency×A=772×A
The total work is considered as 1 unit. Therefore, the remaining work after A days is:
Remaining work=1−772×A
When all three work together, their combined efficiency is:
Combined efficiency of Shahu, Yash, and Dixit=118+124+136
Finding a common denominator (LCM of 18, 24, and 36 is 72):
118=472,124=372,136=272
Thus,
Combined efficiency=472+372+272=972=18 (work per day)
The remaining work is completed in A+445 days, which can be converted to an improper fraction:
445=245⟹A+445=A+245=5A+245
The work done in this time is:
Work done by all three=Combined efficiency×Time=18×5A+245
The remaining work can be expressed as:
1−772A=18×5A+245
Cross-multiplying gives:
(1−772A)×40=5A+24
Expanding and simplifying:
40−28072A=5A+24
Multiplying through by 72 to eliminate the fraction:
2880−280A=360A+1728
Combining like terms:
2880−1728=360A+280A
1152=640A⟹A=1152640=3620=95=1.8
Now substituting A back into the time they worked together:
A+445=95+245=335=6.6 days
Thus, the total number of days all three worked together is:
Total days=6.6 days
Topper's Solved these Questions
Similar Questions
A and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work ?
View SolutionA and B can do a certain work in 12 days. B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work?
View Solution
Knowledge Check
A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 daysA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionIf P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?
View SolutionA can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View Solution