A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?
let no of ays taken =x days
3⋅4=4⋅x
x=3⋅44
=3days
answer
Topper's Solved these Questions
- DIRECT AND INVERSE PROPORTIONSBOOK - NCERTCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - SOLVED EXAMPLES
8 Videos
- DIRECT AND INVERSE PROPORTIONSBOOK - NCERTCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - SOLVED EXAMPLES
8 Videos
- DATA HANDLINGBOOK - NCERTCHAPTER - DATA HANDLINGEXERCISE - EXERCISE 5.1
5 Videos
- EXPONENTS AND POWERSBOOK - NCERTCHAPTER - EXPONENTS AND POWERSEXERCISE - SOLVED EXAMPLES
9 Videos
Similar Questions
A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?
View SolutionTwo persons could fit new windows in a house in 3 days.
(i) One of the persons fell ill before the work started. How long would the job take now?
(ii) How many persons would be needed to fit the windows in one day?
View Solution
Knowledge Check
12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?
A2 hrsB3.2 hrsC3 .5 hrsD3 hrs14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
A12 daysB7 daysC9 daysDNone of theseIf 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.
A1B2C3D4
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 days b. 12 days c. 9 days d. 10 days
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution48 people could complete a task in 17 days .After 6 days , 4 of the workers left . How many days from then will it take to complete the task ?
View SolutionThree persons car build a wall in 4 days, how many days four persons will take to complete the same wall ?
View SolutionA certain number of persons can complete a work in 34 days working 9 hours a day. If the number of persons is decreased by 40%, then how many hours a day should the remaining persons work to complete the work in 51 days ?
कुछ व्यक्ति किसी कार्य को एक दिन में 9 घंटे कार्य करते हुए 34 दिनों में पूरा कर सकते हैं | यदि व्यक्तियों की संख्या 40% से कम कर दी जाए, तो शेष व्यक्तियों को इस कार्य को 51 दिनों में पूरा करने के लिए दिन में कितने घंटे कार्य करना पड़ेगा ?
View Solution