A,B and C can complete a job in 20 days, 30 days, and 40 days, respectively. They worked for 6 days and then A left. B and C completed the job. Find B's wages in the total wages of Rs. 20,000 paid to them ( in Rs.)
The correct Answer is:800
To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate B's share of the total wages.
1. Determine the work rates of A, B, and C:
- A can complete the job in 20 days, so A's work rate is 120 of the job per day.
- B can complete the job in 30 days, so B's work rate is 130 of the job per day.
- C can complete the job in 40 days, so C's work rate is 140 of the job per day.
2. Calculate the combined work rate of A, B, and C:
Combined work rate=120+130+140
To add these fractions, we need a common denominator. The least common multiple of 20, 30, and 40 is 120.
120=6120,130=4120,140=3120
Combined work rate=6+4+3120=13120
3. Calculate the work done by A, B, and C in 6 days:
Work done in 6 days=6×13120=78120=1320
This means that after 6 days, 1320 of the job is completed.
4. Calculate the remaining work:
Remaining work=1−1320=720
5. Determine the work rate of B and C together:
B's work rate=130,C's work rate=140
Combined work rate of B and C=130+140
Using a common denominator of 120:
130=4120,140=3120
Combined work rate of B and C=4+3120=7120
6. Calculate the time taken by B and C to complete the remaining work:
Let x be the number of days B and C work together to finish the remaining work.
Work done by B and C in x days=x×7120
Setting this equal to the remaining work:
x×7120=720
To solve for x:
x=720×1207=6 days
7. Total days worked by each person:
- A worked for 6 days.
- B worked for 6+6=12 days.
- C worked for 6+6=12 days.
8. Calculate the total work done by each person:
- Work done by A:
6×120=620=310
- Work done by B:
12×130=1230=25=820
- Work done by C:
12×140=1240=310
9. Calculate the total work done:
Total work=310+820+310=620+820+620=2020=1
10. Calculate the ratio of work done:
- A's share: 310
- B's share: 820=25
- C's share: 310
The ratio of work done by A, B, and C is:
3:4:3
11. Calculate B's wages from the total wages of Rs. 20,000:
- Total parts = 3+4+3=10
- B's share = 4 parts
B's wages=410×20000=8000 Rs.
Final Answer:
B's wages are Rs. 8,000.
- A can complete the job in 20 days, so A's work rate is 120 of the job per day.
- B can complete the job in 30 days, so B's work rate is 130 of the job per day.
- C can complete the job in 40 days, so C's work rate is 140 of the job per day.
Combined work rate=120+130+140
To add these fractions, we need a common denominator. The least common multiple of 20, 30, and 40 is 120.
120=6120,130=4120,140=3120
Combined work rate=6+4+3120=13120
Work done in 6 days=6×13120=78120=1320
This means that after 6 days, 1320 of the job is completed.
Remaining work=1−1320=720
B's work rate=130,C's work rate=140
Combined work rate of B and C=130+140
Using a common denominator of 120:
130=4120,140=3120
Combined work rate of B and C=4+3120=7120
Let x be the number of days B and C work together to finish the remaining work.
Work done by B and C in x days=x×7120
Setting this equal to the remaining work:
x×7120=720
To solve for x:
x=720×1207=6 days
- A worked for 6 days.
- B worked for 6+6=12 days.
- C worked for 6+6=12 days.
- Work done by A:
6×120=620=310
- Work done by B:
12×130=1230=25=820
- Work done by C:
12×140=1240=310
Total work=310+820+310=620+820+620=2020=1
- A's share: 310
- B's share: 820=25
- C's share: 310
3:4:3
- Total parts = 3+4+3=10
- B's share = 4 parts
B's wages=410×20000=8000 Rs.
B's wages are Rs. 8,000.
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 2
19 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)
View SolutionA and B can do a work in 20 days and 30 days respectively. A and B work on alternate days. Find the number of days to complete the work
View Solution
Knowledge Check
P,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)
A1350B1500C9000D1200M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)
A18910B19C1835D18310P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
A12B18C24D27
P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionA and B separately can complete a work in 18 days and 24 days respectively. They both started working and after 4 days A left the work. Remaining work B can complete with the help of Cin5days. If theyget total wages ₹2,880. Then wages of C?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View Solution