Question

40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10 thday 5 men left the job. The work would have been completed in a 170/3 days b 160/3 days c 52 days d 50 days

Text Solution
Verified by Experts

Correct option a 170/3 days Explanation: Let a man can do 1 unit/day. Total work = 40men×40days=1600 units 40 men can do the work in 10 days = 400 units According to question 5 men left after 10 days 35 men can do the work in 10 days = 350 units 30 men can do the work in 10 days = 300 25 men can do the work in 10 days = 250 20 men can do the work in 10 days = 200 Men left 20-5 = 15 and work left = 1600- 1500 = 100 units they will complete in


Related Solutions