40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10 thday 5 men left the job. The work would have been completed in a 170/3 days b 160/3 days c 52 days d 50 days
Correct option a 170/3 days Explanation: Let a man can do 1 unit/day. Total work = 40men×40days=1600 units 40 men can do the work in 10 days = 400 units According to question 5 men left after 10 days 35 men can do the work in 10 days = 350 units 30 men can do the work in 10 days = 300 25 men can do the work in 10 days = 250 20 men can do the work in 10 days = 200 Men left 20-5 = 15 and work left = 1600- 1500 = 100 units they will complete in
Related Solutions
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
View Solution40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
View Solution60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View SolutionIf 30 men working 8 hours a day can complete a piece of work in 10 days, then how many hours per day must 40 men work so that they can complete it in 6 days?
View SolutionIf 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.
View Solutionयदि 40 पुरुष प्रतिदिन 12 घंटे कार्य करते हुए किसी कार्य को 8 दिनों में पूर्ण कर सकते हैं, तो कितने पुरुष प्रतिदिन 4 घंटे कार्य करते हुए - उसी कार्य को 16 दिनों में पूर्ण कर सकते हैं?
View Solution25 men can do a piece of work in 50 days. In how many days will 10 men complete the work?
View SolutionA, B and C can do a piece of work in 24, 30 and 40 days respectively. They started working together but C left the work 4 days before the completion of the work. In how many days was the work completed?
View Solution16 men can do a piecec of work in 10 days. How many men are needed to complete the work in 40 days?
View Solution5 men can do a piece of work in 4 days, the number of days in which 10 men can complete the work will be
View Solution5 men can do a piece of work in 10 days. How many men will be required to complete the work in 5 days?
View SolutionAtul and Binay together complete a piece of work in 5 days. If Binay alone can complete the same work in 8 days, how many days can Atul take to complete the same work alone? A. 40/3 days B. 20/3 days C. 9 days D. 10 days
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionA, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution25 men can complete a work in 50 days. In how many days will 10 men complete the work?
View SolutionMen and 5 women can complete a piece of work in 12 days. 5 men and 2 women can complete the same work in 9 days. In how many days can only 3 women complete the work?
View Solution240 men working 5 hours a day can complete a piece of work in 20 days. What will be the minimum number of men required to complete the same work in 10 days working 8 hours a day?
View SolutionWorking 8 hours a day, 6 men can do a piece of work in 5 days. In how many days will 10 men complete the same work working 3 hours a day?
View Solution