Question

20 men can do a piece of work in 18 days. They worked together for 3 days then 5 men joined then. In how many more days is the work completed? a 12 days b 14 days c 13 days d 15 days

Text Solution
Verified by Experts

Correct option a 12 daysExplanation: 20 → 18 days ⇒Work done by 20 men working together = 1 work ⇒Work done by them in 3 days working together = 1×3=3 work ⇒Remaining work =18-3=15 work ⇒15 work is to be done by 20+5=25 men ∴ Efficiency of 20 men= 1 Efficiency of 1 men = 1/20Therefore 12 more days will be taken to finish the remaining workAlternate:- 20 men can do 18 days So total work = 18×20 =360 20 men 3 days work = 20×3 =60 Remaining work = 360-60=300 After joining 5 men total men = 20+5so 300/25 = 12 days


Related Solutions