A and B together can dig a trench in 12 days which A alone can dig in 28 days : B alone can dig it in : a 20 days b 21 days c 22 days d 23 days
Correct option b 21 daysExplanation:B’s efficiency = A+B-A= 7 – 3 = 4 units/dayB can dig it alone in
Related Solutions
A and B together can dig a trench in 12 days, which A alone can do in 30 days. In how long B alone can dig it?
View Solution48 men can dig a trench in 14 days then how many days will be taken by 28 men to dig the same clich?
View Solution18 laborers can dig a ditch in 108 days, 54 workers can dig this trench in how many days
View Solution10 people can dig a trench in 6 days. How many people can dig it in 4 days?
View SolutionA and B together can do a job in 12 days. B alone can finish it in 28 days. In how many days can A alone finish the work?
(a)21 days
(b)19 days
(c)20 days
(d)none of these
View Solution30 workers can dig a trench in 5 days. How many workers will be required to dig it in 6 days?
View SolutionIf 10 persons can dig 8 feet trench in 12 days, then how many days will 8 persons take to dig 6 feet trench?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionIf 15 men can dig a well in 20 days, then how many men are needed to dig this well in 12 days?
View Solution12 men can dig a pond in 8 days. How many men can dig it in 6 days?
View SolutionIf 12 men can dig a pond in 8 days, then 18 men can dig it in 6 days.
View SolutionA and B together can do a piece of work in 12 days. A alone works for 8 days and B alone can do the rest of the work in 20 days, then in how many days will B alone finish the whole work?
View SolutionA alone can paint a wall in 50 days B alone can do it in 10 days. If A, B and C together can paint the wall in 6.25 days, then in how many days can C alone paint the wall?
View SolutionA, B and C working together can complete a piece of work in 10 days. A alone can complete the work in 20 days and B alone in 30 days. In how many days will C alone complete the work?
View SolutionIf A alone can do a piece of work in 16 days, B alone can do it in 20 days and C alone can do it in 24 days. In how many days can all three together finish the work?
View SolutionA can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View SolutionA and B together can complete a piece of work in 12 days. A alone can complete it in 20 days if B works only for half a day every day, then in how many days will A and B together complete the work?
View SolutionA and B together can fill a pit in 12 days. A alone can fill it in 20 days. If B works only for half a day a day, then in how many days will A and B together fill the pit?
View Solution