Question
30 men can complete a work in 16 days. Six days after they started working, 15 more men joined them. How many days will they now take to complete the remaining work?
A
5 days
B
20/3 days
C
8 days
D
10/3 days
Text Solution
5 days
20/3 days
8 days
10/3 days
Calculation:
Total Work = 30 × 16 = 480 units
Work done in 1 day = units
Work done in 6 days = = units
Remaining work = 1 - = units
Work remaining = × 480 = 300 units
Total men = 30 + 15 = 45
Days required = = days
∴ days are needed to complete the remaining tasks.