Question

30 men can complete a work in 16 days. Six days after they started working, 15 more men joined them. How many days will they now take to complete the remaining work?

A

5 days

B

20/3 days

C

8 days

D

10/3 days

Text Solution
Verified by Experts

Calculation:

Total Work = 30 × 16 = 480 units

Work done in 1 day =  1 16 units

Work done in 6 days =  6 16 3 8 units

Remaining work = 1 - 3 8 = 5 8 units

Work remaining = 5 8  × 480 = 300 units

Total men = 30 + 15 = 45

Days required =  300 45 = 20 3 days

20 3 days are needed to complete the remaining tasks.

Updated on:21/07/2023