Question
Diptesh and Tushar working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, Diptesh beginning, in how many days, the work will be completed?
A
11
B
10
C
43/4
D
41/4
Text Solution
11
10
43/4
41/4
Given:
Diptesh's rate = 1/9 work/day
Tushar's rate = 1/12 work/day
Formula:
Combined work in two days = Diptesh's 1 day work + Tushar's 1 day work
Calculation:
⇒ The combined work in two days: 1/9 + 1/12
⇒ LCM of 9 and 12 = 36
⇒ (4/36 + 3/36) = 7/36 work in 2 days
⇒ Full cycles to finish the work = Total work / Work done in two days = 1 / (7/36) = 36/7
⇒ Days taken for full cycles = floor(36/7) × 2 = 5 × 2 = 10 days
⇒ Remaining work after 5 cycles: 1 - (35/36) = 1/36
⇒ On the 11th day, Diptesh works, completing more than the remaining work as he can do 1/9 per day.
So, time taken by Diptesh to complete the remaining work = (1/36)/(1/9) = 1/4 days
Thus, total days required = 10 + 1/4 = 41/4 days
Hence, option 4 is the correct answer.