Question

Diptesh and Tushar working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, Diptesh beginning, in how many days, the work will be completed?

A

11

B

10

C

43/4

D

41/4

Text Solution
Verified by Experts

Given:

Diptesh's rate = 1/9 work/day

Tushar's rate = 1/12 work/day

Formula:

Combined work in two days = Diptesh's 1 day work + Tushar's 1 day work

Calculation:

⇒ The combined work in two days: 1/9 + 1/12

⇒ LCM of 9 and 12 = 36

⇒ (4/36 + 3/36) = 7/36 work in 2 days

⇒ Full cycles to finish the work = Total work / Work done in two days = 1 / (7/36) = 36/7

⇒ Days taken for full cycles = floor(36/7) × 2 = 5 × 2 = 10 days

⇒ Remaining work after 5 cycles: 1 - (35/36) = 1/36

⇒ On the 11th day, Diptesh works, completing more than the remaining work as he can do 1/9 per day.

So, time taken by Diptesh to complete the remaining work = (1/36)/(1/9) = 1/4 days

Thus, total days required = 10 + 1/4 = 41/4 days

Hence, option 4 is the correct answer.

Updated on:21/07/2023