Twelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
12
16
20
30
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done, which is calculated as the product of the number of men, the number of hours they work per day, and the number of days they work.
Step 1: Calculate the total work done in terms of man-hours
We know that:
- 12 men work for 8 hours a day for 18 days.
The total work done (in man-hours) can be calculated as:
Total Work=Number of Men×Hours per Day×Days
Substituting the given values:
Total Work=12×8×18
Step 2: Calculate the total work
Now, let's calculate the total work:
12×8=96(man-hours per day)
96×18=1728(total man-hours)
Step 3: Set up the equation for the second scenario
Now we need to find out how many days (let's call it d2) it will take for 24 men working 6 hours a day to complete the same amount of work (1728 man-hours).
Using the same formula for work:
Total Work=Number of Men×Hours per Day×Days
For the second scenario:
1728=24×6×d2
Step 4: Calculate the work done by 24 men in 6 hours
Calculating the work done by 24 men in 6 hours:
24×6=144(man-hours per day)
Step 5: Set up the equation to solve for d2
Now we can substitute this back into our equation:
1728=144×d2
Step 6: Solve for d2
To find d2, divide both sides by 144:
d2=1728144
Step 7: Calculate d2
Calculating d2:
d2=12
Final Answer
Thus, 24 men working 6 hours a day can complete the same work in 12 days.
---
We know that:
- 12 men work for 8 hours a day for 18 days.
Total Work=Number of Men×Hours per Day×Days
Substituting the given values:
Total Work=12×8×18
Now, let's calculate the total work:
12×8=96(man-hours per day)
96×18=1728(total man-hours)
Now we need to find out how many days (let's call it d2) it will take for 24 men working 6 hours a day to complete the same amount of work (1728 man-hours).
Total Work=Number of Men×Hours per Day×Days
For the second scenario:
1728=24×6×d2
Calculating the work done by 24 men in 6 hours:
24×6=144(man-hours per day)
Now we can substitute this back into our equation:
1728=144×d2
To find d2, divide both sides by 144:
d2=1728144
Calculating d2:
d2=12
Thus, 24 men working 6 hours a day can complete the same work in 12 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ASSESSMENT TESTS (TEST 1)12videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
Knowledge Check
- Question 1 - Select One
Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
A18B10C16D8 - Question 2 - Select One
Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
A18B10C16D8 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
30 men working 5 h a day can do a task in 16 days. In how many days will 40 men working 6h a day do the same task?
View Solution20 Men can do a piece of work in 25 days, in how many days will 10 men do it?
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution