Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
A
18
B
10
C
16
D
8
Text Solution
The correct Answer is:D
We have M1D1H1W1=M2D2H2W2
M1=16,D1=15,H1=6
M2=18,D2=?H2=10 and W1=W2=1
16×15×61=18×D2×101
⇒D2=16×15×618×10 = 8 days
Hence the correct option is (d).
|
Updated on:21/07/2023
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ASSESSMENT TESTS (TEST 2)12videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - CONCEPT APPLICATION (LEVEL 3)30videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
Knowledge Check
- Question 1 - Select One
Twelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
A12B16C20D30 - Question 2 - Select One
Twelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
A12B16C20D30 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
If 52 men can do a piece of work in 35 days, in how many days 28 men will do it ?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution