Doubtnut Promotions Sticky

On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20


To solve the problem step by step, we will use the concept of work done, which can be expressed as:

Work=Men×Days×Hours per day

Step 1: Calculate the total work done in the first scenario.
In the first scenario, we have:
- Number of men (M1) = 15
- Number of days (D1) = 20
- Hours worked per day (H1) = 10

Using the formula for work, we can calculate the total work (W):

W=M1×D1×H1=15×20×10

Calculating this:

W=15×20=300
W=300×10=3000 man-hours

Step 2: Set up the equation for the second scenario.
In the second scenario, we have:
- Number of men (M2) = 30
- Number of days (D2) = ? (this is what we need to find)
- Hours worked per day (H2) = 5

Using the same work formula, we have:

W=M2×D2×H2

Substituting the known values:

3000=30×D2×5

Step 3: Solve for D2.
Now we can simplify the equation:

3000=30×5×D2
3000=150×D2

To find D2, we divide both sides by 150:

D2=3000150

Calculating this gives:

D2=20

Conclusion:
Thus, 30 men can complete the work in 20 days if they work 5 hours per day.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days
  • Question 2 - Select One

    45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?

    A10
    B16
    C18
    D15
  • Question 3 - Select One

    12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?

    A18
    B12
    C24
    DCannot be determined