Doubtnut Promotions Sticky

If 4 workers can make 42 toys in 6 days then24 workers can make 42 toys in

A

3 days

B

1 days

C

2 days

D

212days

Text Solution
Verified by Experts

The correct Answer is:B

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    14 workers can make 1400 toys in 5 days. One day after they started the work 14 more workers joined them. How many days will they take to complete the remaining work ?

    A2 days
    B3 days
    C4 days
    D312 days
  • Question 2 - Select One

    14 workers can build a wall in 42 days. One worker can build it in

    A3 day
    B147 day
    C294 day
    D588 day
  • Question 3 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days