Doubtnut Promotions Sticky

A farmer can plough a field working 6 hours per day in 18 days. The worker has to work how many hours per day to finish the same work in 12 days ?

A

7 hrs

B

9 hrs

C

11 hrs

D

13 hrs

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to determine how many hours the farmer must work each day to complete the same amount of work in 12 days instead of 18 days.

Step 1: Calculate the total amount of work done in hours
The farmer works for 6 hours each day for 18 days. Thus, the total work done can be calculated as:
Total Work=Days×Hours per Day=18days×6hours/day=108hours

Step 2: Set up the equation for the new scenario
Now, we want to find out how many hours per day (let's call this x) the farmer needs to work to complete the same amount of work (108 hours) in 12 days. The equation will be:
Total Work=New Days×New Hours per Day
Substituting the values we have:
108hours=12days×xhours/day

Step 3: Solve for x
To find x, we can rearrange the equation:
x=108hours12days=9hours/day

Conclusion
Thus, the farmer needs to work 9 hours per day to finish the work in 12 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?

    A12 hours
    B10 hours
    C11 hours
    D13 hours
  • Question 2 - Select One

    If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours
  • Question 3 - Select One

    Working 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?

    A5
    B7
    C8
    D6