Getting Image
Please Wait...

Home

>

English

>

Class 8

>

Maths

>

Chapter

>

Time And Work

>

A can do a piece of work in 25...

Updated On: 27-06-2022

Get Answer to any question, just click a photo and upload the photo and get the answer completely free,

UPLOAD PHOTO AND GET THE ANSWER NOW!

Loading Books

Answer

Step by step solution by experts to help you in doubt clearance & scoring excellent marks in exams.

Transcript

so a can do a piece of work in 25 days B can finish it in 20 days and they work together for 5 days and then ago and we have to find in how many days will be finish the remaining work so they can complete work is equal to in 25 days so one day work of a will be 1.25 1 by 25 of the work of the total work and B can complete a work in 20 days sau bees one day work of B will be equal to 1 by 20 of the total work and a and b is one day work work will be equal to one day work of a plus one day

that is equal to 1 by 25 + 1 by 20 work show on solving this by taking LCM of 25 and 20 as hundred we have 25 into 400 plus 20 into 500 show 9 by hundred of the work so now they work together for 5 days and then he goes away so there 5 days work will be equal to a and b is 5 day work will be equal to the one day work is 9 by 100 into the five workers in 25 of the total work this is equal to 9 by 5 15 2009 by 20 of the work

is done by A and B in 5 days and then a left so we will we will complete the work in 20 days so we have to find out in how many days will be do the remaining work so the work remaining will be equal to so this part of work is being completed so the work left will be equal to the total work total work minus the this work 9 by 20 of the work so we have the total work will be equal to 1 minus 9 by 20 of the work is remaining so on solving this we have 20 - taking lc-ms 20 we have 20 and 21 is 20 - 9 this is equal to 20 - 9 10 11 by 20 so this is the remaining work

which we have to do alone so we finishes the whole work work in 20 days so this is the remaining work so we finishes 11 by 20 of the work is equal to 20 into 11 by 20 days show this 20 and 21 cancel out to be finishes remaining work work in 11 days thank you

Click here to get PDF DOWNLOAD for all questions and answers of this chapter - RD SHARMA ENGLISH Class 8 TIME AND WORK

Click here to get PDF DOWNLOAD for all questions and answers of this Book - RD SHARMA ENGLISH Class 8 MATHS
Comments

Add a public comment...

By using this site you agree to the use of cookies. Check our Cookie Policy for more details