Doubtnut Promotions Sticky

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A and B in one day
- A can complete the work in 25 days, so A's one day work = 125.
- B can complete the work in 20 days, so B's one day work = 120.

Hint: To find the work done by each person in one day, take the reciprocal of the number of days they take to complete the work.

Step 2: Calculate the combined work done by A and B in one day
- Combined work of A and B in one day = A's one day work + B's one day work
- Combined work = 125+120.

Hint: When adding fractions, find a common denominator to combine them.

Step 3: Find the least common multiple (LCM) of 25 and 20
- The LCM of 25 and 20 is 100.
- Convert the fractions:
- 125=4100
- 120=5100

Hint: To convert fractions to a common denominator, multiply the numerator and denominator by the necessary factor.

Step 4: Add the fractions
- Combined work = 4100+5100=9100.

Hint: After finding a common denominator, simply add the numerators.

Step 5: Calculate the work done by A and B in 5 days
- Work done in 5 days = 5×9100=45100=920.

Hint: To find the total work done over multiple days, multiply the daily work by the number of days worked.

Step 6: Determine the remaining work
- Total work is considered as 1 (whole work).
- Remaining work = Total work - Work done in 5 days
- Remaining work = 1920=2020920=1120.

Hint: To find the remaining work, subtract the completed work from the total work.

Step 7: Calculate the time taken by B to finish the remaining work
- B's work rate is 120 (B can finish the whole work in 20 days).
- Time taken by B to finish the remaining work = Remaining work / B's one day work
- Time = 1120120=11 days.

Hint: To find the time taken to complete a certain amount of work, divide the amount of work by the work rate.

Final Answer:
B will finish the remaining work in 11 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions