Doubtnut Promotions Sticky

A and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by each pair of workers, then find the total work done by all three workers together, and finally calculate the time taken by each worker individually.

Step 1: Write down the equations for work done by pairs
Let:
- A and B together can complete the work in 12 days.
- B and C together can complete the work in 15 days.
- C and A together can complete the work in 20 days.

From this, we can express the work done in one day by each pair:
- Work done by A and B in one day = 112
- Work done by B and C in one day = 115
- Work done by C and A in one day = 120

Step 2: Set up the equations
We can represent the work done by each pair as:
1. A+B=112 (Equation 1)
2. B+C=115 (Equation 2)
3. C+A=120 (Equation 3)

Step 3: Add all three equations
Now, we will add all three equations:
(A+B)+(B+C)+(C+A)=112+115+120
This simplifies to:
2A+2B+2C=112+115+120

Step 4: Find the LCM and calculate the right side
To add the fractions on the right side, we need to find the least common multiple (LCM) of 12, 15, and 20. The LCM is 60.

Now, converting each fraction:
- 112=560
- 115=460
- 120=360

Adding these gives:
5+4+360=1260=15

Step 5: Solve for A + B + C
Now we have:
2A+2B+2C=15
Dividing both sides by 2:
A+B+C=110

This means that together, A, B, and C can complete 110 of the work in one day. Therefore, they will complete the work in:
10 days

Step 6: Calculate individual work rates
Now we need to find how long each person takes to complete the work individually.

For C:
Subtract Equation 1 from A+B+C:
C=(A+B+C)(A+B)=110112
Finding the LCM of 10 and 12, which is 60:
C=6560=160
So, C takes 60 days to complete the work.

For A:
Subtract Equation 2 from A+B+C:
A=(A+B+C)(B+C)=110115
Finding the LCM of 10 and 15, which is 30:
A=3230=130
So, A takes 30 days to complete the work.

For B:
Subtract Equation 3 from A+B+C:
B=(A+B+C)(C+A)=110120
Finding the LCM of 10 and 20, which is 20:
B=2120=120
So, B takes 20 days to complete the work.

Final Results
- A takes 30 days to complete the work.
- B takes 20 days to complete the work.
- C takes 60 days to complete the work.
- Together, they can complete the work in 10 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions