A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:7513 days


To solve the problem step by step, we will first determine the work done by each pair of workers (A and B, B and C, A and C) and then find out how long it will take for all three (A, B, and C) to complete the work together.

1. Determine the work done by each pair:
- A and B can complete the work in 8 days. Therefore, their one day work is:
A+B=18
- B and C can complete the work in 12 days. Therefore, their one day work is:
B+C=112
- A and C can complete the work in 16 days. Therefore, their one day work is:
A+C=116

2. Add the equations:
- Now, we will add all three equations:
(A+B)+(B+C)+(A+C)=18+112+116
- This simplifies to:
2A+2B+2C=18+112+116

3. Calculate the right side:
- To add the fractions, we need a common denominator. The least common multiple (LCM) of 8, 12, and 16 is 48.
- Convert each fraction:
18=648,112=448,116=348
- Now add them:
648+448+348=1348

4. Substitute back into the equation:
- Now we have:
2A+2B+2C=1348
- Dividing both sides by 2 gives:
A+B+C=1396

5. Find the time taken by A, B, and C together:
- The time taken to complete the work when A, B, and C work together is the reciprocal of their one day work:
Time=1A+B+C=11396=9613
- This can be simplified to:
96÷13=7513 days

Final Answer:
A, B, and C together can complete the work in 7513 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Together X and Y can complete a work in 9 days, Y and Z in 12 days and X and Z in 18 days. Who is the most efficient worker among X, Y and Z?

    AX
    BY
    CZ
    DCannot be determined