A can do 78 of work in 28 days, B can do 56 of the same work in 20 days. The number of days they will take to complete if they do it together is .
1537 days
1735 days
1457 days
1357 days
The correct Answer is:D
To solve the problem step by step, we need to determine the work rates of A and B, and then find out how long it will take them to complete the work together.
Step 1: Determine the total work in terms of units
Let's assume the total work is represented by 1 unit.
Step 2: Calculate A's work rate
A can do 78 of the work in 28 days. Therefore, the amount of work A can do in one day is:
Work done by A in one day=7/828=78×28=7224=132 units per day
Step 3: Calculate B's work rate
B can do 56 of the work in 20 days. Therefore, the amount of work B can do in one day is:
Work done by B in one day=5/620=56×20=5120=124 units per day
Step 4: Calculate the combined work rate of A and B
Now, we can find their combined work rate by adding their individual work rates:
Combined work rate=Work done by A in one day+Work done by B in one day=132+124
To add these fractions, we need a common denominator. The least common multiple of 32 and 24 is 96.
Converting the fractions:
132=396(since 1×3=3 and 32×3=96)
124=496(since 1×4=4 and 24×4=96)
Now, adding these fractions:
Combined work rate=396+496=796 units per day
Step 5: Calculate the time taken to complete the work together
If A and B work together, they complete 796 of the work in one day. To find out how many days it will take to complete 1 unit of work, we take the reciprocal of their combined work rate:
Time taken=1 unit796 units per day=967 days
Step 6: Final answer
Calculating 967:
967≈13.71 days
Thus, A and B together will take approximately 13.71 days to complete the work.
Let's assume the total work is represented by 1 unit.
A can do 78 of the work in 28 days. Therefore, the amount of work A can do in one day is:
Work done by A in one day=7/828=78×28=7224=132 units per day
B can do 56 of the work in 20 days. Therefore, the amount of work B can do in one day is:
Work done by B in one day=5/620=56×20=5120=124 units per day
Now, we can find their combined work rate by adding their individual work rates:
Combined work rate=Work done by A in one day+Work done by B in one day=132+124
132=396(since 1×3=3 and 32×3=96)
124=496(since 1×4=4 and 24×4=96)
Combined work rate=396+496=796 units per day
If A and B work together, they complete 796 of the work in one day. To find out how many days it will take to complete 1 unit of work, we take the reciprocal of their combined work rate:
Time taken=1 unit796 units per day=967 days
Calculating 967:
967≈13.71 days
Similar Questions
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View Solution
Knowledge Check
A can do 7/8 of work in 28 days,B can do 5/6 of the same work in 20 days.The number of days they will take to complete if they do it togather is
A(15)37B(17)35C(14)57D(13)57A can do 15th of a work in 4 days and B can do 16th of the same work in 5 days. In how many days they can finish the work, if they work together?
A12B20C15D30A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
A15 daysB10 daysC18 daysD12 days
A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
View SolutionK' can do 3/4th of a work in 6 days and 'I can do 2/5th of the same work in 4 days. How long (in days) will they take, if they work together to finish the work?
View SolutionK' can do 3/4th of a work in 6 days and 'I can do 2/5th of the same work in 4 days. How long (in days) will they take, if they work together to finish the work?
View SolutionA can do 12 of a work in 9 days while B can do 13 of the same same work in 6 days. How long would it take for A and B together to complete the work?
View SolutionA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
View Solution