A can do 78 of work in 28 days, B can do 56 of the same work in 20 days. The number of days they will take to complete if they do it together is .

A

1537 days

B

1735 days

C

1457 days

D

1357 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to determine the work rates of A and B, and then find out how long it will take them to complete the work together.

Step 1: Determine the total work in terms of units
Let's assume the total work is represented by 1 unit.

Step 2: Calculate A's work rate
A can do 78 of the work in 28 days. Therefore, the amount of work A can do in one day is:
Work done by A in one day=7/828=78×28=7224=132 units per day

Step 3: Calculate B's work rate
B can do 56 of the work in 20 days. Therefore, the amount of work B can do in one day is:
Work done by B in one day=5/620=56×20=5120=124 units per day

Step 4: Calculate the combined work rate of A and B
Now, we can find their combined work rate by adding their individual work rates:
Combined work rate=Work done by A in one day+Work done by B in one day=132+124

To add these fractions, we need a common denominator. The least common multiple of 32 and 24 is 96.

Converting the fractions:
132=396(since 1×3=3 and 32×3=96)
124=496(since 1×4=4 and 24×4=96)

Now, adding these fractions:
Combined work rate=396+496=796 units per day

Step 5: Calculate the time taken to complete the work together
If A and B work together, they complete 796 of the work in one day. To find out how many days it will take to complete 1 unit of work, we take the reciprocal of their combined work rate:
Time taken=1 unit796 units per day=967 days

Step 6: Final answer
Calculating 967:
96713.71 days

Thus, A and B together will take approximately 13.71 days to complete the work.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do 7/8 of work in 28 days,B can do 5/6 of the same work in 20 days.The number of days they will take to complete if they do it togather is

    A(15)37
    B(17)35
    C(14)57
    D(13)57
  • A can do 15th of a work in 4 days and B can do 16th of the same work in 5 days. In how many days they can finish the work, if they work together?

    A12
    B20
    C15
    D30
  • A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

    A15 days
    B10 days
    C18 days
    D12 days