Jack takes thrice is much time as Peter and twice as much as Justin to finish a work working together they can finish the work in 15 days. The time (in days) Justin will take to finish the work alone is:
60
85
75
45
The correct Answer is:D
To solve the problem, we need to establish the relationships between the times taken by Jack, Peter, and Justin to complete the work. Let's denote:
- The time taken by Peter to finish the work alone as P days.
- The time taken by Justin to finish the work alone as J days.
- The time taken by Jack to finish the work alone as K days.
From the problem, we know:
1. Jack takes thrice as much time as Peter:
K=3P
2. Jack takes twice as much time as Justin:
K=2J
3. When working together, they can finish the work in 15 days.
Now, we can express the work done by each person in terms of their rates:
- The work rate of Peter is 1P (work done per day).
- The work rate of Justin is 1J.
- The work rate of Jack is 1K.
When they work together, their combined work rate is:
1P+1J+1K=115
Substituting K from the first two equations into the combined work rate equation, we get:
1P+1J+13P=115
To combine the fractions, we first find a common denominator, which is 3PJ:
3J3PJ+3P3PJ+J3PJ=115
This simplifies to:
3J+3P+J3PJ=115
4J+3P3PJ=115
Cross-multiplying gives:
15(4J+3P)=3PJ
Expanding and rearranging:
60J+45P=3PJ
Now, we can express P in terms of J using K=2J:
From K=3P, we have:
P=K3=2J3
Substituting P back into the equation:
60J+45(2J3)=3J(2J3)
60J+30J=2J2
90J=2J2
Dividing by J (assuming J≠0):
90=2J
J=45
Thus, Justin will take 45 days to finish the work alone.
- The time taken by Justin to finish the work alone as J days.
- The time taken by Jack to finish the work alone as K days.
K=3P
K=2J
- The work rate of Justin is 1J.
- The work rate of Jack is 1K.
1P+1J+1K=115
1P+1J+13P=115
3J3PJ+3P3PJ+J3PJ=115
3J+3P+J3PJ=115
4J+3P3PJ=115
15(4J+3P)=3PJ
60J+45P=3PJ
From K=3P, we have:
P=K3=2J3
60J+45(2J3)=3J(2J3)
60J+30J=2J2
90J=2J2
90=2J
J=45
Similar Questions
A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View SolutionA takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in : a. 4 days b. 6 days c. 8 days d. 12 days
View Solution
Knowledge Check
A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 daysA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
A18 daysB21 daysC24 daysD27 days
A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View SolutionA is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?
View Solution18 persons can finish a work in 36 days. How mach time will 12 persons take to finish the same work?
View SolutionA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
View SolutionP is twice as good as Q and together they finish a piece of work in 36 days. The number of days taken by P alone to finish the work?
View Solution