Jack takes thrice is much time as Peter and twice as much as Justin to finish a work working together they can finish the work in 15 days. The time (in days) Justin will take to finish the work alone is:

A

60

B

85

C

75

D

45

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to establish the relationships between the times taken by Jack, Peter, and Justin to complete the work. Let's denote:

- The time taken by Peter to finish the work alone as P days.
- The time taken by Justin to finish the work alone as J days.
- The time taken by Jack to finish the work alone as K days.

From the problem, we know:

1. Jack takes thrice as much time as Peter:
K=3P

2. Jack takes twice as much time as Justin:
K=2J

3. When working together, they can finish the work in 15 days.

Now, we can express the work done by each person in terms of their rates:

- The work rate of Peter is 1P (work done per day).
- The work rate of Justin is 1J.
- The work rate of Jack is 1K.

When they work together, their combined work rate is:
1P+1J+1K=115

Substituting K from the first two equations into the combined work rate equation, we get:
1P+1J+13P=115

To combine the fractions, we first find a common denominator, which is 3PJ:
3J3PJ+3P3PJ+J3PJ=115

This simplifies to:
3J+3P+J3PJ=115
4J+3P3PJ=115

Cross-multiplying gives:
15(4J+3P)=3PJ

Expanding and rearranging:
60J+45P=3PJ

Now, we can express P in terms of J using K=2J:
From K=3P, we have:
P=K3=2J3

Substituting P back into the equation:
60J+45(2J3)=3J(2J3)
60J+30J=2J2
90J=2J2

Dividing by J (assuming J0):
90=2J
J=45

Thus, Justin will take 45 days to finish the work alone.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

    A4 days
    B6 days
    C8 days
    D12 days
  • A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42
  • A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

    A18 days
    B21 days
    C24 days
    D27 days