X and Y together can do a piece of work in 10 days .X is 40 % more efficient than Y.X alone will completes 35 % of the same work in :
6 days
8 days
9 days
5 days
The correct Answer is:A
To solve the problem step by step, we can follow the below approach:
Step 1: Determine the efficiency of X and Y
Given that X is 40% more efficient than Y, we can express their efficiencies in terms of Y's efficiency.
Let the efficiency of Y be EY.
Then, the efficiency of X, EX, can be expressed as:
EX=EY+0.4⋅EY=1.4⋅EY
Step 2: Calculate the combined efficiency of X and Y
When X and Y work together, their combined efficiency is:
EX+Y=EX+EY=1.4EY+EY=2.4EY
Step 3: Calculate the total work done by X and Y together in 10 days
We know that X and Y together can complete the work in 10 days. Therefore, the total work W can be calculated as:
W=EX+Y×Time=2.4EY×10=24EY
Step 4: Calculate the work done by X alone
Now, we need to find out how much work X can complete alone. We know that X will complete 35% of the total work W:
Work done by X=0.35W=0.35×24EY=8.4EY
Step 5: Calculate the time taken by X to complete 35% of the work
To find the time T taken by X to complete this work, we can use the formula:
T=WorkEfficiency=8.4EY1.4EY
The EY cancels out:
T=8.41.4=6 days
Final Answer
Thus, X alone will complete 35% of the same work in 6 days.
---
Given that X is 40% more efficient than Y, we can express their efficiencies in terms of Y's efficiency.
Then, the efficiency of X, EX, can be expressed as:
EX=EY+0.4⋅EY=1.4⋅EY
When X and Y work together, their combined efficiency is:
EX+Y=EX+EY=1.4EY+EY=2.4EY
We know that X and Y together can complete the work in 10 days. Therefore, the total work W can be calculated as:
W=EX+Y×Time=2.4EY×10=24EY
Now, we need to find out how much work X can complete alone. We know that X will complete 35% of the total work W:
Work done by X=0.35W=0.35×24EY=8.4EY
To find the time T taken by X to complete this work, we can use the formula:
T=WorkEfficiency=8.4EY1.4EY
The EY cancels out:
T=8.41.4=6 days
Thus, X alone will complete 35% of the same work in 6 days.
Similar Questions
Knowledge Check
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 daysA can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
A17 daysB18 daysC15 daysD12 daysA can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A12B16C18D15
A can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View SolutionA can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?
View SolutionNiNAl can alone complete a work in 20 days. Suresh is 25% more efficient than her. He can complete the work in __ days.
View SolutionP alone can do a work in 60 days. P is 40% less efficient than Q. In how many days can Q alone do the same work?
View Solution