14 men complete a work in 18 days. If 21 men are employed, then the time required to complete the same work will be:
14 days
10 days
15 days
12 days
The correct Answer is:D
To solve the problem step by step, we can use the concept of man-days, which is the product of the number of men and the number of days they work.
1. Identify the given data:
- Number of men (M1) = 14
- Time taken by these men (T1) = 18 days
- Number of men employed later (M2) = 21
- Time taken by these men (T2) = ?
2. Calculate total work in man-days:
- Total work = M1 × T1
- Total work = 14 men × 18 days = 252 man-days
3. Set up the equation for the second scenario:
- We know that the total work remains the same, so:
- Total work = M2 × T2
- 252 man-days = 21 men × T2
4. Solve for T2:
- Rearranging the equation gives us:
- T2 = Total work / M2
- T2 = 252 man-days / 21 men
5. Perform the division:
- T2 = 12 days
Conclusion:
The time required to complete the same work with 21 men is 12 days.
- Number of men (M1) = 14
- Time taken by these men (T1) = 18 days
- Number of men employed later (M2) = 21
- Time taken by these men (T2) = ?
- Total work = M1 × T1
- Total work = 14 men × 18 days = 252 man-days
- We know that the total work remains the same, so:
- Total work = M2 × T2
- 252 man-days = 21 men × T2
- Rearranging the equation gives us:
- T2 = Total work / M2
- T2 = 252 man-days / 21 men
- T2 = 12 days
The time required to complete the same work with 21 men is 12 days.
Similar Questions
Knowledge Check
15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be
A7 daysB8 daysC10 daysD12 daysIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D2224 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men
7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View SolutionIf 3 men and 7 women can complete a work in 10 days and 4 men and 6 women need 8 days to complete the same work. In how many days will 10 women complete the same work?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution