14 men complete a work in 18 days. If 21 men are employed, then the time required to complete the same work will be:

A

14 days

B

10 days

C

15 days

D

12 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we can use the concept of man-days, which is the product of the number of men and the number of days they work.

1. Identify the given data:
- Number of men (M1) = 14
- Time taken by these men (T1) = 18 days
- Number of men employed later (M2) = 21
- Time taken by these men (T2) = ?

2. Calculate total work in man-days:
- Total work = M1 × T1
- Total work = 14 men × 18 days = 252 man-days

3. Set up the equation for the second scenario:
- We know that the total work remains the same, so:
- Total work = M2 × T2
- 252 man-days = 21 men × T2

4. Solve for T2:
- Rearranging the equation gives us:
- T2 = Total work / M2
- T2 = 252 man-days / 21 men

5. Perform the division:
- T2 = 12 days

Conclusion:
The time required to complete the same work with 21 men is 12 days.

|


Similar Questions


Knowledge Check

  • 15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be

    A7 days
    B8 days
    C10 days
    D12 days
  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • 24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men