7 men and 6 women together can complete a piece of work in 8 days and work done by a women in one day is half the work done by a man in one day. If 8 men and 4 women started working and after 3 days 4 men left the work and 4 new women joined them, in how many more days will the remaining work be completed?
7 days
6 days
5.25 days
6.25 days
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Determine the work done by men and women
Given:
- 7 men and 6 women can complete the work in 8 days.
- The work done by a woman in one day is half the work done by a man in one day.
Let the work done by one man in one day be 2x (units of work).
Then, the work done by one woman in one day is x.
Step 2: Calculate total work
The total work done by 7 men and 6 women in one day is:
Work per day=7×2x+6×x=14x+6x=20x
Since they complete the work in 8 days, the total work W is:
W=Work per day×Number of days=20x×8=160x
Step 3: Work done in the first 3 days
Now, 8 men and 4 women start working. The work done by them in one day is:
Work per day=8×2x+4×x=16x+4x=20x
In 3 days, the total work done is:
Total work done in 3 days=20x×3=60x
Step 4: Calculate remaining work
The remaining work after 3 days is:
Remaining work=Total work−Work done in 3 days=160x−60x=100x
Step 5: Work after 3 days
After 3 days, 4 men leave, and 4 new women join. Now, the workforce consists of:
- Remaining men: 8−4=4
- New women: 4+4=8
The work done by the remaining workers in one day is:
Work per day=4×2x+8×x=8x+8x=16x
Step 6: Calculate days required to finish remaining work
To find the number of days required to complete the remaining work of 100x:
Days required=Remaining workWork per day=100x16x=10016=6.25 days
Final Answer
The remaining work will be completed in 6.25 days.
---
Given:
- 7 men and 6 women can complete the work in 8 days.
- The work done by a woman in one day is half the work done by a man in one day.
Then, the work done by one woman in one day is x.
The total work done by 7 men and 6 women in one day is:
Work per day=7×2x+6×x=14x+6x=20x
Since they complete the work in 8 days, the total work W is:
W=Work per day×Number of days=20x×8=160x
Now, 8 men and 4 women start working. The work done by them in one day is:
Work per day=8×2x+4×x=16x+4x=20x
In 3 days, the total work done is:
Total work done in 3 days=20x×3=60x
The remaining work after 3 days is:
Remaining work=Total work−Work done in 3 days=160x−60x=100x
After 3 days, 4 men leave, and 4 new women join. Now, the workforce consists of:
- Remaining men: 8−4=4
- New women: 4+4=8
Work per day=4×2x+8×x=8x+8x=16x
To find the number of days required to complete the remaining work of 100x:
Days required=Remaining workWork per day=100x16x=10016=6.25 days
The remaining work will be completed in 6.25 days.
Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View Solution8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 days
View Solution
Knowledge Check
8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed
A7 daysB6 daysC5.25 daysD3.7 days8 men and 4 women together can complete a piece of work in
6 days. The work done by a man in one day is diuble the
work done by a woman in one day. If 8 men and 4 women
started working and after 2 days 4 men left and 4 new women
joined, in how many more days will the work be complete?A5 daysB8 daysC6 daysD4 days8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
A5 daysB8 daysC6 daysD4 days
10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
View Solution