7 men and 6 women together can complete a piece of work in 8 days and work done by a women in one day is half the work done by a man in one day. If 8 men and 4 women started working and after 3 days 4 men left the work and 4 new women joined them, in how many more days will the remaining work be completed?

A

7 days

B

6 days

C

5.25 days

D

6.25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Determine the work done by men and women
Given:
- 7 men and 6 women can complete the work in 8 days.
- The work done by a woman in one day is half the work done by a man in one day.

Let the work done by one man in one day be 2x (units of work).
Then, the work done by one woman in one day is x.

Step 2: Calculate total work
The total work done by 7 men and 6 women in one day is:
Work per day=7×2x+6×x=14x+6x=20x
Since they complete the work in 8 days, the total work W is:
W=Work per day×Number of days=20x×8=160x

Step 3: Work done in the first 3 days
Now, 8 men and 4 women start working. The work done by them in one day is:
Work per day=8×2x+4×x=16x+4x=20x
In 3 days, the total work done is:
Total work done in 3 days=20x×3=60x

Step 4: Calculate remaining work
The remaining work after 3 days is:
Remaining work=Total workWork done in 3 days=160x60x=100x

Step 5: Work after 3 days
After 3 days, 4 men leave, and 4 new women join. Now, the workforce consists of:
- Remaining men: 84=4
- New women: 4+4=8

The work done by the remaining workers in one day is:
Work per day=4×2x+8×x=8x+8x=16x

Step 6: Calculate days required to finish remaining work
To find the number of days required to complete the remaining work of 100x:
Days required=Remaining workWork per day=100x16x=10016=6.25 days

Final Answer
The remaining work will be completed in 6.25 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • 8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

    A7 days
    B6 days
    C5.25 days
    D3.7 days
  • 8 men and 4 women together can complete a piece of work in
    6 days. The work done by a man in one day is diuble the
    work done by a woman in one day. If 8 men and 4 women
    started working and after 2 days 4 men left and 4 new women
    joined, in how many more days will the work be complete?

    A5 days
    B8 days
    C6 days
    D4 days
  • 8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?

    A5 days
    B8 days
    C6 days
    D4 days