10 men can complete project in 12 days 12 children can complete same in 16 days and 8 womwn can in 20 days 5 men and 12 children started project if after 4 days 8 children were replaced by 4 women in how many days remaining project was completed
(4)2/5
(5)1/2
(7)1/2
(6)2/3
The correct Answer is:D
To solve the problem step by step, we need to calculate the work done by men, children, and women, and then determine how much work is left after certain days.
Step 1: Calculate the total work in terms of man-days
- 10 men can complete the project in 12 days.
- Total work = 10 men × 12 days = 120 man-days.
Step 2: Calculate the work done by 5 men and 12 children in 4 days
- 12 children can complete the project in 16 days.
- Total work = 12 children × 16 days = 192 child-days.
- Work done by 1 child in 1 day = 1/192 of the project.
- Work done by 5 men in 1 day:
- Work done by 1 man in 1 day = 1/120 of the project.
- Work done by 5 men in 1 day = 5 × (1/120) = 5/120 = 1/24 of the project.
- Work done by 12 children in 1 day:
- Work done by 12 children in 1 day = 12 × (1/192) = 12/192 = 1/16 of the project.
- Total work done by 5 men and 12 children in 1 day:
- Total work in 1 day = (1/24) + (1/16).
- To add these fractions, find a common denominator (48):
- (1/24) = 2/48
- (1/16) = 3/48
- Total work in 1 day = 2/48 + 3/48 = 5/48 of the project.
- Work done in 4 days:
- Work done in 4 days = 4 × (5/48) = 20/48 = 5/12 of the project.
Step 3: Calculate the remaining work
- Remaining work = Total work - Work done in 4 days
- Remaining work = 1 - 5/12 = 7/12 of the project.
Step 4: Calculate the new team composition after 4 days
- After 4 days, 8 children are replaced by 4 women.
- Work done by 4 women:
- 8 women can complete the project in 20 days.
- Total work = 8 women × 20 days = 160 woman-days.
- Work done by 1 woman in 1 day = 1/160 of the project.
- Work done by 4 women in 1 day = 4 × (1/160) = 4/160 = 1/40 of the project.
- Work done by 4 children:
- Work done by 4 children in 1 day = 4 × (1/192) = 4/192 = 1/48 of the project.
- Total work done by 4 women and 4 children in 1 day:
- Total work in 1 day = (1/40) + (1/48).
- Find a common denominator (240):
- (1/40) = 6/240
- (1/48) = 5/240
- Total work in 1 day = 6/240 + 5/240 = 11/240 of the project.
Step 5: Calculate the time required to complete the remaining work
- Remaining work = 7/12 of the project.
- Time required = Remaining work / Work done in 1 day
- Time required = (7/12) ÷ (11/240) = (7/12) × (240/11) = (7 × 20) / 11 = 140/11 days.
Final Answer:
The remaining project was completed in approximately 12.73 days (or 12 days and 16 hours).
- 10 men can complete the project in 12 days.
- Total work = 10 men × 12 days = 120 man-days.
- 12 children can complete the project in 16 days.
- Total work = 12 children × 16 days = 192 child-days.
- Work done by 1 child in 1 day = 1/192 of the project.
- Work done by 5 men in 1 day:
- Work done by 1 man in 1 day = 1/120 of the project.
- Work done by 5 men in 1 day = 5 × (1/120) = 5/120 = 1/24 of the project.
- Work done by 12 children in 1 day = 12 × (1/192) = 12/192 = 1/16 of the project.
- Total work in 1 day = (1/24) + (1/16).
- To add these fractions, find a common denominator (48):
- (1/24) = 2/48
- (1/16) = 3/48
- Total work in 1 day = 2/48 + 3/48 = 5/48 of the project.
- Work done in 4 days = 4 × (5/48) = 20/48 = 5/12 of the project.
- Remaining work = Total work - Work done in 4 days
- Remaining work = 1 - 5/12 = 7/12 of the project.
- After 4 days, 8 children are replaced by 4 women.
- Work done by 4 women:
- 8 women can complete the project in 20 days.
- Total work = 8 women × 20 days = 160 woman-days.
- Work done by 1 woman in 1 day = 1/160 of the project.
- Work done by 4 women in 1 day = 4 × (1/160) = 4/160 = 1/40 of the project.
- Work done by 4 children in 1 day = 4 × (1/192) = 4/192 = 1/48 of the project.
- Total work in 1 day = (1/40) + (1/48).
- Find a common denominator (240):
- (1/40) = 6/240
- (1/48) = 5/240
- Total work in 1 day = 6/240 + 5/240 = 11/240 of the project.
- Remaining work = 7/12 of the project.
- Time required = Remaining work / Work done in 1 day
- Time required = (7/12) ÷ (11/240) = (7/12) × (240/11) = (7 × 20) / 11 = 140/11 days.
The remaining project was completed in approximately 12.73 days (or 12 days and 16 hours).
Similar Questions
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution
Knowledge Check
12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D1015 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D3212 men can finish a project in 20 days. 18 women can finish
the same project in 16 days and 24 children can finish it in 18
days. 8 women and 16 children worked for 9 days and then
left. In how many will 10 men coplete the remaining project ?A1012B10C9D1112
8 men can do a work in 12 days while 20 women can do it in 10 days. In how many days can 12 men and 15 women complete the same work.
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?
View Solution4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
View Solution2 men can complete a piece of work in 6 days. 2 women can
complete the same piece of work in 9 days. Where as 3
children can complete the same piece of work in 8 days. 3
women and 4 children worked together for 1 day. If only
men were to finish the remaining work in day, how many
total men would be required?
View Solution