10 men can complete project in 12 days 12 children can complete same in 16 days and 8 womwn can in 20 days 5 men and 12 children started project if after 4 days 8 children were replaced by 4 women in how many days remaining project was completed

A

(4)2/5

B

(5)1/2

C

(7)1/2

D

(6)2/3

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to calculate the work done by men, children, and women, and then determine how much work is left after certain days.

Step 1: Calculate the total work in terms of man-days
- 10 men can complete the project in 12 days.
- Total work = 10 men × 12 days = 120 man-days.

Step 2: Calculate the work done by 5 men and 12 children in 4 days
- 12 children can complete the project in 16 days.
- Total work = 12 children × 16 days = 192 child-days.
- Work done by 1 child in 1 day = 1/192 of the project.

- Work done by 5 men in 1 day:
- Work done by 1 man in 1 day = 1/120 of the project.
- Work done by 5 men in 1 day = 5 × (1/120) = 5/120 = 1/24 of the project.

- Work done by 12 children in 1 day:
- Work done by 12 children in 1 day = 12 × (1/192) = 12/192 = 1/16 of the project.

- Total work done by 5 men and 12 children in 1 day:
- Total work in 1 day = (1/24) + (1/16).
- To add these fractions, find a common denominator (48):
- (1/24) = 2/48
- (1/16) = 3/48
- Total work in 1 day = 2/48 + 3/48 = 5/48 of the project.

- Work done in 4 days:
- Work done in 4 days = 4 × (5/48) = 20/48 = 5/12 of the project.

Step 3: Calculate the remaining work
- Remaining work = Total work - Work done in 4 days
- Remaining work = 1 - 5/12 = 7/12 of the project.

Step 4: Calculate the new team composition after 4 days
- After 4 days, 8 children are replaced by 4 women.
- Work done by 4 women:
- 8 women can complete the project in 20 days.
- Total work = 8 women × 20 days = 160 woman-days.
- Work done by 1 woman in 1 day = 1/160 of the project.
- Work done by 4 women in 1 day = 4 × (1/160) = 4/160 = 1/40 of the project.

- Work done by 4 children:
- Work done by 4 children in 1 day = 4 × (1/192) = 4/192 = 1/48 of the project.

- Total work done by 4 women and 4 children in 1 day:
- Total work in 1 day = (1/40) + (1/48).
- Find a common denominator (240):
- (1/40) = 6/240
- (1/48) = 5/240
- Total work in 1 day = 6/240 + 5/240 = 11/240 of the project.

Step 5: Calculate the time required to complete the remaining work
- Remaining work = 7/12 of the project.
- Time required = Remaining work / Work done in 1 day
- Time required = (7/12) ÷ (11/240) = (7/12) × (240/11) = (7 × 20) / 11 = 140/11 days.

Final Answer:
The remaining project was completed in approximately 12.73 days (or 12 days and 16 hours).

|


Similar Questions


Knowledge Check

  • 12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

    A16
    B12
    C18
    D10
  • 15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • 12 men can finish a project in 20 days. 18 women can finish
    the same project in 16 days and 24 children can finish it in 18
    days. 8 women and 16 children worked for 9 days and then
    left. In how many will 10 men coplete the remaining project ?

    A1012
    B10
    C9
    D1112