The questions given below contain two statements numbered I and II giving certain data. You have to decide whether the data given in the statements are sufficient to answer the question. Give answer
In how many days can 18 men and 14 women complete a piece of work?
I 9 men and 7 women together can complete the same piece of work in 6 days. II. 2 men and 4 women together can complete the same piece of work in 16 days.
if statement I alone is sufficient but statement II alone is not sufficient.
if statement II alone is sufficient but statement I alone is not sufficient.
if either statement I or II is sufficient.
if both statement I and II together are not suficient.
The correct Answer is:A
To determine how many days 18 men and 14 women can complete a piece of work, we will analyze the two statements provided.
Step 1: Analyze Statement I
Statement I states that 9 men and 7 women can complete the work in 6 days.
1. Calculate the total work done in terms of man-days:
- If 9 men and 7 women complete the work in 6 days, the total work can be expressed as:
Total Work=Number of Workers×Days=(9+7) workers×6 days=96 worker-days
2. Determine the work rate of men and women:
- Let the work done by one man in one day be m and by one woman be w.
- The equation based on Statement I becomes:
6(9m+7w)=96⟹9m+7w=16(1)
Step 2: Analyze Statement II
Statement II states that 2 men and 4 women can complete the work in 16 days.
1. Calculate the total work done in terms of man-days for Statement II:
- If 2 men and 4 women complete the work in 16 days, the total work can be expressed as:
Total Work=(2+4) workers×16 days=48 worker-days
2. Determine the work rate of men and women:
- The equation based on Statement II becomes:
16(2m+4w)=48⟹2m+4w=3(2)
Step 3: Solve the Equations
Now we have two equations:
1. 9m+7w=16 (from Statement I)
2. 2m+4w=3 (from Statement II)
We can solve these equations to find the values of m and w.
1. From equation (2), we can express m in terms of w:
2m+4w=3⟹m=3−4w2(3)
2. Substitute equation (3) into equation (1):
9(3−4w2)+7w=16
27−36w2+7w=16
27−36w+14w=32⟹−22w=5⟹w=−522(not valid)
Step 4: Use the Validity of Statements
Since we cannot find valid values for m and w from both statements combined, we need to check if either statement alone is sufficient.
- Statement I alone is sufficient because it provides a direct relationship between men and women.
- Statement II alone is not sufficient as it does not provide enough information to determine the work rate of men and women.
Conclusion
Thus, we can conclude that:
- Only Statement I is sufficient to answer the question.
Final Answer
The answer is that Statement I alone is sufficient to determine how many days 18 men and 14 women can complete the work.
Statement I states that 9 men and 7 women can complete the work in 6 days.
- If 9 men and 7 women complete the work in 6 days, the total work can be expressed as:
Total Work=Number of Workers×Days=(9+7) workers×6 days=96 worker-days
- Let the work done by one man in one day be m and by one woman be w.
- The equation based on Statement I becomes:
6(9m+7w)=96⟹9m+7w=16(1)
Statement II states that 2 men and 4 women can complete the work in 16 days.
- If 2 men and 4 women complete the work in 16 days, the total work can be expressed as:
Total Work=(2+4) workers×16 days=48 worker-days
- The equation based on Statement II becomes:
16(2m+4w)=48⟹2m+4w=3(2)
Now we have two equations:
1. 9m+7w=16 (from Statement I)
2. 2m+4w=3 (from Statement II)
2m+4w=3⟹m=3−4w2(3)
9(3−4w2)+7w=16
27−36w2+7w=16
27−36w+14w=32⟹−22w=5⟹w=−522(not valid)
Since we cannot find valid values for m and w from both statements combined, we need to check if either statement alone is sufficient.
- Statement II alone is not sufficient as it does not provide enough information to determine the work rate of men and women.
Thus, we can conclude that:
- Only Statement I is sufficient to answer the question.
The answer is that Statement I alone is sufficient to determine how many days 18 men and 14 women can complete the work.
Similar Questions
If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.
View SolutionThree men can complete a piece of work in 18 days. 6 boys can also complete the same piece of work in 18 days. In how many days will 4 men and 4 boys together complete the same piece of work?
View Solution
Knowledge Check
In how many days 14 men can complete a piece of work?
I. If 18 women can complete the same piece of work in 24 days
II. If 28 children can complete the same piece of work in 56 days.AIf the Statement I alone is sufficient to answer the question but the Statement II alone is not sufficientBIf the Statement II alone is sufficient to answer the question but the Statement I alone is not sufficientCIf both the Statements I and II together are needed to answer the questionDIf you cannot get the answer from the statements I and II together but need even more dataTen women can complete a picce of work in 15 days. Six men can complete the same piece of work in 10 days. In how many days can 5 women and six men together complete the piece of work?
A15 daysB7.5 daysC9 daysD12.5 days2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
A12 daysB16 daysC18 daysD19 days
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View SolutionIn how many days can 4 women complete a work?
I. 4 men and 4 women can complete the same work in 12 days.
II. 10 women can complete the same work in 16 days
View Solution12 men alone can complete a piece of work in 6 days. Whereas
10 men and 21 women together take 3 days to complete the
same piece of work. In how many days can 12 women alone
complete the piece of work?
View SolutionThe question given below contain two statements giving certain data. You have to decide whether the data given in the statements are sufficient for answering the question ?
15 men and 18 women together can complete a work in 10 days. How many days will it take 9 men and 14 women together to complete the same work?
I. 30 men can complete the work in 13 days
II. The amount of work done by a man in one day is 3/4 of the work done by a woman in one day.
View Solution