A can do a piece of work in 14 days. Other person B is 20% more efficient than A. In how many days will A and B together complete the same piece of work?
91011days
101011days
6411days
121011day
The correct Answer is:B
To solve the problem step by step, we need to determine how long it will take for A and B to complete the work together.
Step 1: Determine A's Efficiency
A can complete the work in 14 days. Therefore, A's efficiency can be calculated as:
Efficiency of A=1 work14 days=114
Step 2: Determine B's Efficiency
B is 20% more efficient than A. To find B's efficiency, we first calculate 20% of A's efficiency:
20% of A's efficiency=0.2×114=0.214=170
Now, we add this to A's efficiency to find B's efficiency:
Efficiency of B=Efficiency of A+20% of A's efficiency=114+170
To add these fractions, we need a common denominator. The least common multiple of 14 and 70 is 70:
114=570
Now we can add:
Efficiency of B=570+170=670=335
Step 3: Calculate Combined Efficiency of A and B
Now that we have the efficiencies of both A and B, we can find their combined efficiency:
Combined Efficiency=Efficiency of A+Efficiency of B=114+335
Again, we need a common denominator. The least common multiple of 14 and 35 is 70:
114=570,335=670
Now we can add:
Combined Efficiency=570+670=1170
Step 4: Calculate Time Taken by A and B Together
The total work can be represented as 1 unit of work. To find the time taken by A and B together to complete the work, we use the formula:
Time=Total WorkCombined Efficiency=11170=7011
This means A and B together will take 7011 days to complete the work.
Final Answer
Thus, A and B together will complete the work in 6411 days.
---
A can complete the work in 14 days. Therefore, A's efficiency can be calculated as:
Efficiency of A=1 work14 days=114
B is 20% more efficient than A. To find B's efficiency, we first calculate 20% of A's efficiency:
20% of A's efficiency=0.2×114=0.214=170
Now, we add this to A's efficiency to find B's efficiency:
Efficiency of B=Efficiency of A+20% of A's efficiency=114+170
To add these fractions, we need a common denominator. The least common multiple of 14 and 70 is 70:
114=570
Now we can add:
Efficiency of B=570+170=670=335
Now that we have the efficiencies of both A and B, we can find their combined efficiency:
Combined Efficiency=Efficiency of A+Efficiency of B=114+335
Again, we need a common denominator. The least common multiple of 14 and 35 is 70:
114=570,335=670
Now we can add:
Combined Efficiency=570+670=1170
The total work can be represented as 1 unit of work. To find the time taken by A and B together to complete the work, we use the formula:
Time=Total WorkCombined Efficiency=11170=7011
This means A and B together will take 7011 days to complete the work.
Thus, A and B together will complete the work in 6411 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 days - Question 2 - Select One
A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A12B16C18D15 - Question 3 - Select One
A can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A24B32C18D15
A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionA can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
View SolutionA can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?
View SolutionA can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View Solution